Developer RERA record

Godrej Properties

Godrej Properties has 154 RERA-registered projects: weak Gurugram delivery record (3/18 projects with OC); 82 projects under construction, Bengaluru averaging 49% construction; 44 projects past their declared completion date — a significant track-record flag. All figures are the developer's own regulator filings.

Flagged
Delivery signal
82
Under construction
3
Completed / delivered
44
Past declared date
84%
Bengaluru inventory booked
95
RERA complaints filed

Under construction

Under construction — 82 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

Mumbai: 2.67/5 ★★★☆☆ (6 MouthShut reviews)  ·  Pune: 1.24/5 ★☆☆☆☆ (204 MouthShut reviews)

ProjectCityProgress / possession
GODREJ PARK RETREATBengaluru99%
Godrej SplendourBengaluru93%
Godrej Park Retreat Phase 2Bengaluru89%
Godrej Woodland Phase 2Bengaluru87%
Godrej WoodlandBengaluru87%
Godrej AthenaBengaluru50%
ARAVYA ESTATEBengaluru40%
Godrej Splendour Phase IIBengaluru33%
Godrej WoodscapesBengaluru24%
GODREJ LAKESIDE ORCHARDBengaluru24%
Godrej Woodscapes Phase 2Bengaluru23%
GODREJ TIARABengaluru9%
GODREJ WOODSBengaluru2%
GODREJ AVELINEBengaluru1%
GODREJ PARKSHIREBengaluru1%
Forest Grove AT Godrej Park GreensPunepossession by Sep 2027
Godrej Aqua VistaPunepossession by Mar 2032
Godrej Ascend Phase 1Mumbaipossession by Apr 2028
Godrej Ascend Phase 2Mumbaipossession by Dec 2028
Godrej Ascend Phase 3Mumbaipossession by Oct 2029
Godrej Ascend Phase 4Mumbaipossession by Dec 2029
Godrej Avenue Eleven - Tower AMumbaipossession by Dec 2028
Godrej Avenue Eleven - Tower BMumbaipossession by Dec 2029
Godrej BayviewMumbaipossession by Dec 2027
Godrej BlissMumbaipossession by Nov 2029
Godrej CarmichaelMumbaipossession by Dec 2030
Godrej CarnivalPunepossession by Sep 2026
Godrej Eden Estate Phase 3Punepossession by Mar 2027
Godrej ElarisPunepossession by May 2032
Godrej Emerald WatersPunepossession by Feb 2029
Godrej Eternal PalmsMumbaipossession by Dec 2032
Godrej Evergreen SquarePunepossession by Oct 2030
Godrej ExquisiteMumbaipossession by Sep 2026
Godrej Five GardensMumbaipossession by Dec 2028
Godrej Golf Side EstateMumbaipossession by Sep 2026
Godrej Golf Side Estate IIMumbaipossession by Dec 2028
Godrej GreensPunepossession by Sep 2026
Godrej Hill RetreatPunepossession by Dec 2026
Godrej Hill Retreat 2Punepossession by Mar 2027
Godrej Hillside 3Punepossession by Feb 2028
Godrej Hillview EstateMumbaipossession by Mar 2027
Godrej Horizon Phase IMumbaipossession by May 2028
Godrej Horizon Phase IIMumbaipossession by Jun 2029
Godrej Horizon Phase IIIMumbaipossession by Jun 2031
Godrej IvaraPunepossession by Aug 2032
Godrej MeadowsPunepossession by Dec 2026
Godrej Meadows- Phase 2Punepossession by Dec 2026
Godrej NurturePunepossession by Sep 2026
Godrej Nurture - Tower 2Mumbaipossession by Mar 2031
Godrej Nurture - Tower 3Mumbaipossession by Mar 2031
Godrej Park GreensPunepossession by Mar 2028
Godrej Park SpringsPunepossession by Sep 2029
Godrej Reserve Wing 1Mumbaipossession by Jun 2030
Godrej Reserve Wing 2Mumbaipossession by Jun 2031
Godrej Reserve Wing 3Mumbaipossession by Jun 2030
Godrej Reserve Wing 4Mumbaipossession by Jun 2030
Godrej Reserve Wing 5Mumbaipossession by Jun 2030
Godrej River CrestPunepossession by Jun 2030
Godrej River RoyalePunepossession by Mar 2029
Godrej Riviera Phase 1Mumbaipossession by Dec 2026
Godrej SerenePunepossession by Jun 2027
Godrej Sky Greens Phase 1Punepossession by Dec 2026
Godrej Sky Greens Phase 2Punepossession by Dec 2026
Godrej Sky TerracesMumbaipossession by Mar 2029
Godrej SkylinePunepossession by Jul 2029
Godrej SkyshoreMumbaipossession by Dec 2031
Godrej SquareMumbaipossession by Oct 2028
Godrej Trilogy SeafrontMumbaipossession by Dec 2034
Godrej Trilogy SeaturfMumbaipossession by Dec 2033
Godrej UpavanMumbaipossession by Jun 2028
Godrej Urban ParkMumbaipossession by Sep 2026
Godrej Urban RetreatPunepossession by Oct 2027
Godrej Varanya Phase 1Mumbaipossession by Dec 2032
Godrej Varanya Phase 2Mumbaipossession by Jun 2034
Godrej Vihaa Phase 5Mumbaipossession by Dec 2031
Godrej VistasMumbaipossession by Dec 2029
Godrej Woodside Estate Phase 1Mumbaipossession by Mar 2028
Godrej Woodside Estate Phase 2Mumbaipossession by Mar 2028
Godrej WoodsvillePunepossession by Nov 2026
MadhubanPunepossession by Sep 2026
Mamurdi Mhada NorthPunepossession by Mar 2027
Sparkle AT Godrej SerenePunepossession by Dec 2027
Considering a specific Godrej Properties project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (3)click to expand
ProjectCityStatus
GODREJ MERIDIEN- IGurugramOC issued
GODREJ NATURE PLUSGurugramOC issued
GODREJ SUMMITGurugramOC issued
Past declared date (44)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Godrej AirBengaluru2022-12
Godrej AvenuesBengaluru2021-05
Godrej EternityBengaluru2020-04
Zest at Godrej EternityBengaluru2022-10
Life+ at Godrej EternityBengaluru2022-10
Godrej AquaBengaluru2024-01
GODREJ AIR NXTBengaluru2023-07
Godrej Woodland Phase 2 (87.0% built)Bengaluru2025-12
Godrej Woodland (87.0% built)Bengaluru2025-12
Godrej Royale WoodsBengaluru2025-04
Godrej 24Pune2022-09
Godrej Alive AMumbai2025-12
Godrej Alive BMumbai2025-12
Godrej Alive CMumbai2025-12
Godrej Alive EMumbai2025-12
Godrej BoulevardPune2025-09
Godrej CentralMumbai2021-03
Godrej City Panvel Ph.1Mumbai2022-12
Godrej Country EstateMumbai2026-04
Godrej Eden Estate Phase 1Pune2026-02
Godrej Eden Estate Phase 2Pune2026-02
Godrej ElementsPune2022-12
Godrej Emerald ThaneMumbai2026-06
Godrej Green CovePune2026-06
Godrej Green VistasPune2026-05
Godrej Hillside 1Pune2024-10
Godrej Hillside 2Pune2024-10
Godrej InfinityPune2020-09
Godrej NestMumbai2025-04
Godrej NirvaanMumbai2024-12
Godrej ParkridgePune2025-09
Godrej Platinum Wing B4Mumbai2022-12
Godrej PranaPune2020-09
Godrej PrimeMumbai2023-05
Godrej RejuvePune2024-03
Godrej RKSMumbai2024-12
Godrej TranquilMumbai2023-06
Godrej TwoMumbai2023-06
Godrej Vihaa Phase 1Mumbai2022-07
Godrej Vihaa Phase 2Mumbai2022-08
Godrej Wood ParkPune2023-11
The Trees Residential Phase 2Mumbai2022-06
The Trees, OriginsMumbai2023-06
The Trees, Residential Phase 1Mumbai2022-06
Registered, no progress filed yet (25)click to expand
ProjectCity
GODREJ AIR PHASE-IGurugram
GODREJ AIR PHASE-IIGurugram
GODREJ AIR PHASE-IIIGurugram
GODREJ AIR PHASE-IVGurugram
GODREJ ALIRAGurugram
GODREJ ARIA & 101 (VOL. III)Gurugram
GODREJ ARISTOCRATGurugram
GODREJ HABITATGurugram
GODREJ MERIDIEN- IIGurugram
GODREJ MERIDIEN PHASE IIIGurugram
GODREJ MIRAYAGurugram
GODREJ SAMARISGurugram
GODREJ SORAGurugram
GODREJ VRIKSHYAGurugram
GODREJ ZENITHGurugram
Godrej VanantaraBengaluru
GODREJ RIVERINENoida
GODREJ MAJESTY GH-01/B,C,D,E.J AND K SEC 12 -G NOIDANoida
GODREJ ARDENNoida
GODREJ TROPICAL ISLENoida
GODREJ JARDINIANoida
GODREJ PARKSHIREBengaluru
ARAVYA ESTATEBengaluru
Godrej Royale WoodsBengaluru
Godrej Regent ParkBengaluru

RERA complaints & orders

Regulatory record

95 total complaints filed — more complaints than 92% of builders we track.

63
MahaRERA complaints
32
Karnataka RERA complaints

Most recent orders on the RERA register:

ProjectComplainantBenchDate
Sky Gardens at Godrej VihaaPremrajan KurupHON. MEMBER IICopyright

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Godrej Properties's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.