Bangalore/Project record

K-RERA · the public record

JYOTHI NIVAS

Bengaluru South · SAI KIRAN CONSTRUCTIONS

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
63%construction reportedQ3 2025 filing
14units not bookedof 14 · Q3 2025 filing
30 Jun 2026declared completionK-RERA registration · read 26 Oct 2026

Free project details

Registration read 26 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 26 Oct 2026

Registered units and project size

4 BHK
7
3 BHK
7

Filed categories, unchanged · K-RERA registration · read 26 Oct 2026

The whole registration

0.6registered acres

24.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for JYOTHI NIVAS

K-RERA · PRM/KA/RERA/1251/310/PR/061125/008228

Project facts and comparisons

On the register

Declared completion30 June 2026
Land area2,311 sq m (0.6 acres)
Homes registered14
Tower/wing entries1
Unit mix7 × 4 BHK, 7 × 3 BHK

In context

Density24.5 homes per acre
Density in context6th percentile of 791 Bengaluru South projects (median 77.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units14Total inventory registered with K-RERA.
Official carpet area2,468 sqmTotal carpet area reported for the project.
Official built-up area5,416 sqmUseful scale context when comparing density and project cost.
Registered land area2,311 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.64Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)28Separate filed counts; these categories may overlap and are not added together.
Covered-parking field28Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberAd.Com./RJH/1052/22-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date16-12-2022
Project start date19-08-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK750%1,388 sqm
3 BHK750%1,093 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
JYOTHI NIVAS4142814.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 14 official flat/unit rows, matching the 14 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK71,507.0-1,814.0 sqft1,354.8-1,649.0 sqft14
4 BHK71,923.5-2,346.8 sqft1,867.3-2,175.4 sqft14

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
JYOTHI NIVAS141,507.0-2,346.8 sqft1,354.8-2,175.4 sqft28
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101JYOTHI NIVAS03 BHK1,699.7 sqft1,520.4 sqft2
102JYOTHI NIVAS03 BHK1,699.7 sqft1,510.7 sqft2
103JYOTHI NIVAS03 BHK1,699.7 sqft1,510.7 sqft2
104JYOTHI NIVAS03 BHK1,699.7 sqft1,520.4 sqft2
105JYOTHI NIVAS03 BHK1,507.0 sqft1,354.8 sqft2
106JYOTHI NIVAS03 BHK1,650.1 sqft1,437.0 sqft2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

⚠ 3 of 21 compliance document slots are filed as under process / not yet usable: Brochure, ESCOM/Electricity, KWSSB/Water.

2 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2026 — which has passed with no OC on file.

See the filed approval statuses and linked documents →

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Statutory approval status

RERA filing

0 of 2 applicable approvals are marked Approved in the filing. Other recorded statuses: Water supply and sewage board: To Be Applied; KPTCL- BESCOM: To Be Applied. Check the linked documents for their scope and validity.

8 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardTo Be Applied-View NOC
KPTCL- BESCOMTo Be Applied-View NOC

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantRadhakrishna Tantry0240121990Bengaluru Urban, Karnataka - 560085
EngineerKumar C GBCC/BL-3.6/SE-0349/2019-202001Bengaluru Urban, Karnataka - 560090
ArchitectDinesh Kumar S.,CA/2005/363812005Bengaluru Urban, Karnataka - 560019
ContractorSai Kiran Constructions-2017Bengaluru Urban, Karnataka - 560098

Builder track record

RERA filing

Sai Kiran has 2 other K-RERA-registered projects in our records (average reported construction progress 100%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress63% → 63% (+0 pts)
Units sold/booked as registered0/14 (0%)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹122.4 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Karnataka Bank Ltd.. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 17 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre12 km
Electronic City17 km
Bellandur–Marathahalli belt19 km
Outer Ring Road / Manyata19 km
Whitefield IT hub26 km
Kempegowda Int'l Airport39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sai Kiran.
Sai Kiran has 3 projects registered in Bangalore, 1 completed, 1 past RERA deadline.

Other projects by this builder in Bangalore

Garden Square
Filing overdue · 100% built · 84% sold

Other RERA-registered projects in Koramangala

SJR Primecorporation PVT LTD Palazza PH2
SJR Primecorporation PVT LTD Palazza PH3
SJR Primecorporation PVT LTD Palazzacity

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 26 Oct 2026. Document and inventory dates are shown in their sections.