Bangalore/Project record

K-RERA · the public record

MIGHTY YUVA

Bengaluru East · MIGHTY HOMES

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
75%construction reportedQ1 2026 filing
0units not bookedof 0 · Q1 2026 filing
30 Sep 2027declared completionK-RERA registration · read 26 Oct 2026

Free project details

Registration read 26 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Sep 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 26 Oct 2026

Registered units and project size

Flats
68

Filed categories, unchanged · K-RERA registration · read 26 Oct 2026

The whole registration

0.9registered acres

73.8registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for MIGHTY YUVA

K-RERA · PRM/KA/RERA/1251/446/PR/010725/007889

Project facts and comparisons

On the register

Declared completion30 September 2027
Land area3,730 sq m (0.9 acres)
Homes registered68
Tower/wing entries1
Unit mix68 × Flats

In context

Density73.8 homes per acre
Density in context47th percentile of 1123 Bengaluru East projects (median 75.5)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units68Total inventory registered with K-RERA.
Official carpet area6,077 sqmTotal carpet area reported for the project.
Official built-up area10,419 sqmUseful scale context when comparing density and project cost.
Registered land area3,730 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)75Separate filed counts; these categories may overlap and are not added together.
Covered-parking field75Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBDA/NM/AS/AA-1/TS-4/E/58/2024-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date14-02-2025
Project start date01-04-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Flats68100%6,077 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
MIGHTY YUVA4687515 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 68 official flat/unit rows, matching the 68 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK3266.9-77.5 sqm42.0-47.1 sqm32
3 BHK3294.7-113.5 sqm57.0-69.6 sqm32
4 BHK4123.2 sqm73.5 sqm4

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
MIGHTY YUVA6866.9-123.2 sqm42.0-73.5 sqm68
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1MIGHTY YUVA03 BHK113.5 sqm69.6 sqm1
2MIGHTY YUVA03 BHK106.7 sqm63.6 sqm1
3MIGHTY YUVA03 BHK111.9 sqm69.6 sqm1
4MIGHTY YUVA03 BHK96.6 sqm57.7 sqm1
5MIGHTY YUVA03 BHK94.7 sqm57.0 sqm1
6MIGHTY YUVA02 BHK77.5 sqm45.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

⚠ 5 of 21 compliance document slots are filed as under process / not yet usable: Board Resolution for Authorized Signatory/Certificate of Authorization, Brochure, Relinquishment Deed, ESCOM/Electricity, KWSSB/Water.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

1 of 1 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

9 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
KPTCL- BESCOMApproved02-07-2025bescom noc.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantLOKESH REDDY N2286622005Chittoor, Andhra Pradesh - 517501
EngineerRoshanAM30262672022Ramanagara, Karnataka - 562117
ArchitectSathish Babu BCA/2018/1035212019Bengaluru Urban, Karnataka - 560075
ContractorSivaprasad-2020Bengaluru Urban, Karnataka - 560067

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹2.14 Cr collected from buyers, ₹2.14 Cr withdrawn from the project's escrow account.

Construction progress56% → 75% (+19 pts)
Buyer collections in available QPRs₹4.17 Cr
Escrow withdrawals in available QPRs₹3.31 Cr (0.79x collections)
  • Construction progress moved from 56% to 75% across the filed QPR window.
  • The builder has drawn 0.79x of buyer collections from escrow (about 79% of the ₹4 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹33.2 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: AU Small Finance Bank. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 7 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Whitefield IT hub7 km
Bellandur–Marathahalli belt12 km
Outer Ring Road / Manyata14 km
MG Road / city centre17 km
Kempegowda Int'l Airport19 km
Electronic City23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mighty Homes.
Mighty Homes has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Kannamangala

Major developers building in Kannamangala

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 26 Oct 2026. Document and inventory dates are shown in their sections.