Bangalore/Project record

K-RERA · the public record

N K Developers

Bengaluru North · N K Developers

Is this the right project?
Which plot should you choose?

Read the free RERA facts below. For help choosing a plot or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best plots.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
99%construction reportedQ1 2026 filing
31 Dec 2028declared completionK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q1 2026 to Q1 2026

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 25 Oct 2026

RERA details for N K Developers

K-RERA · PRM/KA/RERA/1251/309/PR/040526/008617

Project facts and comparisons

On the register

Declared completion31 December 2028

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Approved plan numberBDA/TPM/PRL-43/2024-2025/2114/25-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date30-08-2025
Project start date01-08-2025

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

11 of 21 compliance document slots are filed as Not Applicable; the remaining 10 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

4 of 4 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

7 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved04-12-2026Water NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved16-09-2025KSPCB.pdf
KPTCL- BESCOMApproved24-04-2026Power supply NOC.pdf
Horticulture departmentApproved13-03-2026Horticulture department.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantShaik Anjum2793212024Bengaluru Urban, Karnataka - 560024
EngineerSunil Kumar BAM31772492019Bengaluru Urban, Karnataka - 560096

Builder track record

RERA filing

Developers has 62 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Developers”) (average reported construction progress 80%). 20 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress99% → 99% (+0 pts)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Axis Bank Peenya IFSC Code : UTIB0004406 Pin Code : 560058. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 12 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre11 km
Outer Ring Road / Manyata12 km
Bellandur–Marathahalli belt20 km
Electronic City24 km
Whitefield IT hub26 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Developers.
Developers has 54 projects registered in Bangalore, 10 completed.
2 complaints on the K-RERA register against Developers in Bangalore.

Other projects by this builder in Bangalore

36 Park Avenue Phase III
Filing overdue · 100% built
36 Park Avenue Phase-II
Filing overdue · 100% built
A R Pearl Apartment
Filing overdue · 100% built · 71% sold
Avani Abode
Filing overdue · 99% built
Amantran Anant Shubh Vihaar
Filing overdue · 65% built · 7% sold
G9 Vinyas 2
Filing overdue · 100% built

Other RERA-registered projects in Nayanda Halli

Major developers building in Nayanda Halli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.