PALM GROVES

Bengaluru South · KARSTEN HOMES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionK-RERA registration · read 20 Sep 2026
207registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.8registered acres

112.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/171201/001362

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2019
Land area7,476 sq m (1.8 acres)
Homes registered207
Tower/wing entries1

In context

Density112.1 homes per acre
Density in context88th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units207Total inventory registered with K-RERA.
Registered land area7,476 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.45Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)207Separate filed counts; these categories may overlap and are not added together.
Open-parking field24Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date12-01-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
B BLOCK8207207-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 207 official flat/unit rows, matching the 207 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK10862.4-67.6 sqm21.8-27.7 sqm108
2BHK9940.9-53.9 sqm18.9-27.4 sqm99

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
B BLOCK20740.9-67.6 sqm18.9-27.7 sqm207
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
B 101B BLOCK03BHK62.4 sqm27.7 sqm1
B 102B BLOCK03BHK62.5 sqm27.7 sqm1
B 103B BLOCK03BHK62.5 sqm27.7 sqm1
B 104B BLOCK03BHK62.5 sqm26.3 sqm1
B 105B BLOCK03BHK67.6 sqm27.4 sqm1
B 106B BLOCK03BHK62.5 sqm27.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 17 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2019, extended (Section 6 Extension) to 30 Sep 2021 — both dates have passed with no OC on file. The extension on file was granted on 26 May 2020 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/200526/001362) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (8 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
CHANDRA SEKHAR REDDY BATCHU vs M/S.KARSTE HOMES PVT LTDI pray to the respected Chief Head of RERA requested to intervene the matter and justice is prayed for early action against the developers to refund my amount of Rs. 22,25,000/- alongwith preEMI paidAUTHORITY22/07/2026
NATARAJ K vs KARSTEN HOMES PVT LTDSir, please call us and look into our issue and kindly resolve our issue and please help us in getting back our whole of sum of amount (22 lakhs, so far )AUTHORITY19/03/2024
Nataraj K vs Palm grovesTo take action against the espondent for non completion of the project to clear all the loan , charges and mortgage on the schedule property.AUTHORITY15/02/2022
Indranil Das vs KARSTEN HOMES PVT LTD1. Refund of all amounts along with 18% p.a. Interest.AUTHORITY14/05/2025
Roshan Lal Soni vs M/S.KARSTEN HOMES PVT LTD,NoAUTHORITY10/06/2025
VINOD M vs KARSTEN HOMES PVT LTDRefund of amount due on cancellation with interestAUTHORITY08/12/2022
Amitabh vs KARSTEN HOMES PVT LTDAs per the Supreme court verdict, Builder should pay me interest @10% until they gave me possession OR I would want them to refund all amount paid to them plus the interest paid by me.AUTHORITY08/12/2022
Sandeep Roy Choudhury and Deboshree Chakraborty vs KARSTEN HOMES PVT LTD(i) Cancel the Agreement for Sale and Construction Agreement dated August 23, 2019, executed with the Complainants; (ii) Return the total amount disbursed by the Complainants to the RespondentsAUTHORITY08/12/2022

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (5 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/210401/0007855
01-04-2021
RefundPALM GROVESDISPOSED AUTHORITY BENCH4
CMP/210717/0008136
17-07-2021
Delay in handover the Residential ApartmentPALM GROVESDISPOSED AUTHORITY FULLBENCH
CMP/211018/0008446
18-10-2021
Non-Payment of Pre-EMI since March 2020 & delayed delivery of projectPALM GROVESDISPOSED AUTHORITY BENCH4
CMP/220510/0009442
10-05-2022
Non-Payment of Pre-EMI since March 2020 & delayed delivery of project, and breach of the agreementPALM GROVESDISPOSED AUTHORITY BENCH5
CMP/220713/0009743
13-07-2022
Seeking cancellation and refundPALM GROVESDISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRamesha DB -Landmark Architects & Engineers-201422nd Main, JP Nagar 2nd Phase
Structural engineerG. Praveen Kumar -ECO Consultants---

Builder track record

RERA filing

Karsten Homes has 3 other K-RERA-registered projects in our records. 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹4.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank Mejestic (IFSC UTIB0000693, a/c …8907). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City9 km
Bellandur–Marathahalli belt18 km
Whitefield IT hub23 km
MG Road / city centre24 km
Outer Ring Road / Manyata31 km
Kempegowda Int'l Airport47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Karsten Homes.
Karsten Homes has 4 projects registered in Bangalore.
10 complaints on the K-RERA register against Karsten Homes in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Weaver Colony

Major developers building in Weaver Colony

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.