Bangalore/Project record

K-RERA · the public record

S V Paradise

Bengaluru South · S V Builders

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
14 Mar 2022declared completionK-RERA registration · read 25 Oct 2026
20registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

0.2registered acres

98.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for S V Paradise

K-RERA · PRM/KA/RERA/1251/310/PR/190809/002775

Project facts and comparisons

On the register

Declared completion14 March 2022
Land area825 sq m (0.2 acres)
Homes registered20
Tower/wing entries1

In context

Density98.1 homes per acre
Density in context79th percentile of 791 Bengaluru South projects (median 77.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units20Total inventory registered with K-RERA.
Registered land area825 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)22Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date15-03-2019

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
S V Paradise42022-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 20 official flat/unit rows, matching the 20 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK1263.0-80.3 sqm328.0-415.0 sqm12
3BHK885.0-90.9 sqm486.0-530.0 sqm8

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
S V Paradise2063.0-90.9 sqm328.0-530.0 sqm20
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G1S V Paradise13BHK90.9 sqm530.0 sqm1
G2S V Paradise12BHK80.3 sqm403.0 sqm1
G3S V Paradise13BHK85.0 sqm486.0 sqm1
G4S V Paradise12BHK63.0 sqm328.0 sqm1
G5S V Paradise12BHK68.1 sqm413.0 sqm1
101S V Paradise23BHK90.9 sqm530.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

2 of 19 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 14 Mar 2022, extended (Covid Extension) to 14 Dec 2022 — both dates have passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Bundled document listed: All NOCs from Authority
Water & sewage (BWSSB/KWSSB)Bundled document listed: All NOCs from Authority
Fire NOCBundled document listed: All NOCs from Authority
Pollution control (KSPCB)Bundled document listed: All NOCs from Authority
Environmental clearanceBundled document listed: All NOCs from Authority
Airport Authority height clearanceBundled document listed: All NOCs from Authority

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
PANCHANAGOUDA MUDIGOUDAR vs S V Builderskindly give the direction to the Owner and the Developer to form an Association of the Owners under the Karnataka Apartment Ownership Act by executing Deed of Declaration and hand over the common areaAUTHORITY10/06/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectV.SIVA KUMAR-200821st MAINB.S.K. II STAGE, BANGALORE
ContractorC.Guravaiaha-2011Milasandra, Bangalore
Structural engineerSRINIVAS RAO BOLIMUNTA---

Builder track record

RERA filing

Builders has 40 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Builders”) (average reported construction progress 73%). 16 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹22.5 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Union Bank of India BTM Branch (IFSC UBIN0556521, a/c …0517). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest of the listed job hubs is about 6 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Bellandur–Marathahalli belt6 km
MG Road / city centre7 km
Outer Ring Road / Manyata8 km
Whitefield IT hub9 km
Electronic City16 km
Kempegowda Int'l Airport23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Builders.
Builders has 17 projects registered in Bangalore, 3 completed.
1 complaints on the K-RERA register against Builders in Bangalore.

Other projects by this builder in Bangalore

Casa Luxuria
Filing overdue · 100% built · 34% sold
Northernsky Evolve
Filing overdue · 25% built · 0% sold
Northernsky Westvalley
Filing overdue · 100% built · 86% sold
Rama Ranga
Filing overdue · 13% built · 31% sold
RED Stone Enclave
Filing overdue · 100% built · 50% sold

Other RERA-registered projects in Ramamurthy Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.