Bangalore/Project record

K-RERA · the public record

Shilpitha Royal Oak

Hosakote · Maithri Developers

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
10 Sep 2020declared completionK-RERA registration · read 25 Oct 2026
60registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

0.8registered acres

77.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for Shilpitha Royal Oak

K-RERA · PRM/KA/RERA/1250/304/PR/190219/002386

Project facts and comparisons

On the register

Declared completion10 September 2020
Land area3,136 sq m (0.8 acres)
Homes registered60
Tower/wing entries1

In context

Density77.4 homes per acre
Density in context49th percentile of 117 Hosakote projects (median 78.8)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units60Total inventory registered with K-RERA.
Registered land area3,136 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~2.24Sanctioned floor-area ratio (≈7,022 sqm sanctioned FAR area ÷ 3,136 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)66Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field60Separate filed counts; these categories may overlap and are not added together.
Project start date15-05-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A46066-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 60 official flat/unit rows, matching the 60 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK31641.0-964.0 sqft269.0-443.0 sqft31
3BHK20964.0-1,150.0 sqft451.0-556.0 sqft20
2.5BHK9758.0-937.0 sqft331.0-459.0 sqft9

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A60641.0-1,150.0 sqft269.0-556.0 sqft60
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
'001A03BHK1,043.0 sqft495.0 sqft1
'002A03BHK1,003.0 sqft451.0 sqft1
'003A02.5BHK805.0 sqft362.0 sqft1
'004A02BHK641.0 sqft269.0 sqft1
'005A02BHK679.0 sqft315.0 sqft1
'006A02BHK641.0 sqft315.0 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 16 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 10 Sep 2020, extended (Covid Extension) to 10 Jun 2021 — both dates have passed with no OC on file. An extension application filed on 09 Jan 2026 is pending with K-RERA — until it is approved, the registration stands lapsed.

Approval documents

Electricity (BESCOM/ESCOM)Not identified in the document list
Water & sewage (BWSSB/KWSSB)Not identified in the document list
Fire NOCNot identified in the document list
Pollution control (KSPCB)Document listed: KSPCB
Environmental clearanceNot identified in the document list
Airport Authority height clearanceNot identified in the document list

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
DHARMENDRA GANDROTHU & POORNIMA GANDROTHU vs MAITHRI DEVELOPERSCompletion of the project in all respects, Refund of EMI amount paid by me till completion of project, Maintenance amount collected so far, 20% of flat cost towards delay in handingover.AUTHORITY23/08/2022
SRINIVASAN GANESAN & SINDHIYA vs MAITHRI DEVELOPERSCompletion of the project in all respects, Refund of EMI amount paid by me till completion of project, maintenance amount collected so far, 25% of flat cost towards the delay in completion of projectAUTHORITY23/08/2022
RAJIV KUMAR SHARMA 7 ABHILASHA SHARMA vs MAITHRI DEVELOPERSCompletion of project in all respect. Refund of EMI amount paid by me till completion of the project, refund of maintenance charge, 25% of flat cost towards delay in completion of the project.AUTHORITY23/08/2022
B. KARTHIK vs MAITHRI DEVELOPERSREFUND OF EMI PAID BY ME TILL THE COMPLETION OF PROJECT, REFUND OF MAINTANCE AMOUNT COLLECTED FROM TILL TO DATE AND ALSO REFUND OF 20% FLAT COST TOWARDS THE DELAY IN HANDING OVERAUTHORITY23/08/2022

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (4 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/220222/0009038
22-02-2022
Failure in obtaining Occupancy Certificate and delay in completion of the projectShilpitha Royal OakDISPOSED AUTHORITY BENCH6
CMP/220222/0009040
22-02-2022
DELAY IN COMPLETION OF PROJECT AND FAILURE IN OBTAINING OCCUPANCY CERTIFICATE AND BESCOM CONNECTIONShilpitha Royal OakDISPOSED AUTHORITY BENCH6
CMP/220222/0009041
22-02-2022
FAILURE IN OBTAINING OCCUPANCY CERTIFICATE/ABANDONMENT OF THE PROJECT IN IMPAIRED CONDITIONShilpitha Royal OakDISPOSED AUTHORITY BENCH6
CMP/220223/0009047
23-02-2022
Failure in obtaining OC and delay in completion of the projectShilpitha Royal OakDISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Builder track record

RERA filing

Maithri Developers has 3 other K-RERA-registered projects in our records. 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹27.5 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: STATE BANK OF INDIA Doddanekkundi (IFSC SBIN0015615, a/c …7766). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Whitefield IT hub4 km
Bellandur–Marathahalli belt9 km
Outer Ring Road / Manyata13 km
MG Road / city centre14 km
Electronic City20 km
Kempegowda Int'l Airport22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Maithri Developers.
Maithri Developers has 4 projects registered in Bangalore.
8 complaints on the K-RERA register against Maithri Developers in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.