RERA Property Intelligence Report · Preview

Skylark Ithaca

Ithaca Estates · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/170915/000308

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
Litigation on file
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

1,761
Registered units
₹751.6 Cr
Est. construction cost
Units profiled
16
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units1,761Total inventory registered with K-RERA.
Official carpet area105,637 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area79,621 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.499Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings19Official tower/wing count in the K-RERA detail page.
Parking disclosed1,761 total (1,679 open) — 1.00 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date25-08-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Apartment1,498100%105,637 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 119113113-
Tower 219115115-
Tower 319115115-
Tower 4197575-
Tower 519115115-
Tower 619115115-
Tower 7197676-
Tower 8197979-

Showing first 8 of 19 tower/wing rows.

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 1,761 official flat/unit rows, matching the 1,761 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK987750.9-795.2 sqft303.6-318.1 sqft987
3BHK558944.6-1,485.1 sqft380.8-598.0 sqft558
1BHK211434.2-452.7 sqft181.7-187.4 sqft211
4BHK51,812.8-2,294.7 sqft727.4-919.0 sqft5

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 10117750.9-1,485.1 sqft303.6-598.0 sqft117
Tower 9116452.7-1,439.0 sqft187.4-587.1 sqft116
Tower 11115750.9-1,485.1 sqft303.6-598.0 sqft115
Tower 2115452.7-1,439.0 sqft187.4-587.1 sqft115
Tower 3115750.9-1,485.1 sqft303.6-598.0 sqft115
Tower 5115452.7-1,439.0 sqft187.4-587.1 sqft115
Tower 6115750.9-1,485.1 sqft303.6-598.0 sqft115
Tower 1113750.9-1,485.1 sqft303.6-598.0 sqft113
Tower 12 (Phase II)89452.7-944.6 sqft187.4-380.8 sqft89
Tower 13 (Phase II)89750.9-795.2 sqft303.6-318.1 sqft89
Tower 14 (Phase II)89750.9-795.2 sqft303.6-318.1 sqft89
Tower 15 (Phase II)89452.7-944.6 sqft187.4-380.8 sqft89

Showing first 12 of 19 tower/wing groups.

Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
T1-001Tower 102BHK750.9 sqft303.6 sqft1
T1-002Tower 102BHK795.2 sqft318.1 sqft1
T1-003Tower 102BHK795.2 sqft318.1 sqft1
T1-005Tower 102BHK795.2 sqft318.1 sqft1
T1-006Tower 102BHK795.2 sqft318.1 sqft1
T1-101Tower 112BHK750.9 sqft303.6 sqft1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~839 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a large, multi-tower township — 1761 homes across 19 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 1,761 parking spaces for 1,761 homes (~1.0 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~338 sqft per home; across all 1,761 homes that is ~69% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

All 12 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (39 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Rajendra Gurram vs SKY LARK ITHACAFlat delivery,Rent compensation,delay compensationAUTHORITY29/04/2025
Niyas Ahmed Kambalbasha vs SKYLARK ITHACARefund With InterestAUTHORITY29/04/2025
SNEHANSU BHUSAN CHATTERJEE vs Ithaca Estates Private LimitedGet money back and stop EMIAUTHORITY15/06/2026
Dr Satish J Patil vs Ithaca Estates Private Limited1) Execute the Exit option- memorandum of understanding agreement 2) Reimbrse all the pre-emis with interest 3) foreclose the loan 4) Payment of opportunity cost with interestAUTHORITY15/06/2026
IMMIDI VIDYA vs Ithaca Estates Private LimitedRefundAUTHORITY15/06/2026
Mitalee Chopra and Vikas Vivek vs Ithaca Estates Private Limitedas prayed in the facts of caseAUTHORITY15/06/2026
SACHIDANANDA KRISHNAPPA KANCHAN vs Ithaca Estates Private Limited1) Refund of amount paid by me and Opportunity cost to be paid by the developer 2) Bank Loan takeover OR cancellation of loan in my name refund of disbursed amount 3) Reimbursement of pending pre EMIsAUTHORITY15/06/2026
Mr.Vishal Gupta and Mrs.Varalika Gupta vs Ithaca Estates Private Limited1. Direct the M/s.Skylark Mansions Pvt Ltd & M/s.AUTHORITY15/06/2026
ABHISHEK TEWARI vs Ithaca Estates Private LimitedICICI Bank Loan Pre EMI is requested to be stopped. Bank failed to release the funds based on the inconsistent progress made by the Developer. Expected Refund is approximately 18 Lakhs.AUTHORITY15/06/2026
Chitralekha Mishra vs Ithaca Estates Private LimitedRefund of amount paid by complainants along with interest, Refund of Pre-emi's paid ,Abide terms of Exit Option-MOU , Payment of opportunity cost ,bank loan closure,Refund of all paymentsAUTHORITY15/06/2026
Nilesh Ishverbhai Patel vs Ithaca Estates Private LimitedExit the project by cancelling Agreement, Direct Respondents to refund the sum of Rs. 7,36,492/- along with interest at 18% , Direct the Respondent to discharge to loan and repay the pemiAUTHORITY15/06/2026
Bhupendra Kashinath Ingle vs Ithaca Estates Private LimitedAs prayed in the facts of caseAUTHORITY15/06/2026
Mohammad Sharique Ahmad vs Ithaca Estates Private Limited1. Exit from the project. 2. Refund of Rs. 6,32,276/- at 18% interest 3. Opportunity Cost of Rs. 4,78,778/- 4. Direct Respondent to Discharge the loan amount disbursed 5. Refund of pre-emi along witAUTHORITY15/06/2026
Refund of Booking Amount vs Ithaca Estates Private LimitedHelp to get refund from Builder.AUTHORITY15/06/2026
Mohammad Sharique Ahmad vs Ithaca Estates Private Limited1. a. exit the project and cancellation of the agreement, 2. Refund of sale consideration along with 18% interest pa 3. Direct the Respondent to discharge the loan 4. Opportunity costAUTHORITY15/06/2026
Dindukurthi Radha Krishna babu vs Ithaca Estates Private LimitedDirect the builder to refund advance , reimburce pre-emi & Emi also clear the pending amount due to ICICI Bank loan NoLBBNG00002997860towards both the principal and accrued interestAUTHORITY15/06/2026
mohammad sharique ahmad vs Ithaca Estates Private Limitedretund and exit from the project SKYLARK ITHAKAAUTHORITY15/06/2026
Abdul Mujeeb Khan vs Ithaca Estates Private Limited1. Direct the M/s.Skylark Mansions Pvt Ltd & M/s.Ithaca Estates Pvt Ltd to pay the complainant all the pre-emi’s (1,818,331/-.. Pre-Emi as on today) which the opposite party has failed to reimburse.AUTHORITY15/06/2026
Silgin Sidharthan Moothandassery vs Ithaca Estates Private LimitedRefund of Rs Rs 35,27,127 along with interestAUTHORITY15/06/2026
Nitin Urs vs Ithaca Estates Private Limitedi. Levy penalty on Respondents/developer amounting to five percent of real estate project in terms of Section 60 of the Act and other reliefs as stated in a separate sheet due to restriction of spaceAUTHORITY15/06/2026
Mr Subramanian vs Ithaca Estates Private LimitedRefund and cancellation of the amount Rs 56,33,104AUTHORITY15/06/2026
Roshan Gupta vs Ithaca Estates Private LimitedRefund with compensationAUTHORITY15/06/2026
Jayashankar Prasad Singh vs Skylark Mansion Pvt. Ltddirection to handover possession with damagesAUTHORITY14/12/2024
Kumari Niwedita vs Ithaca Estates Private LimitedRefund of PRE-EMI & stop upcoming PRE-EMIAUTHORITY14/12/2024
LAXMIKANT AGARWAL vs ITHACA ESTATES PRIVATE LIMITEDRefund from Skylark due to non-completion 3yrs pending project. And clearance to me so that I can stop paying pre-emi to bank.AUTHORITY14/02/2025
venkata naga sarat kumar inuguri vs Ithaca Estates Private LimitedCancellation and release of money I have paid (with interest)AUTHORITY13/12/2025
Shammi Malhotra vs Ithaca Estates Private LimitedRefund of the amount as per below schedule along with interest i.e Rs 9510717 with with interestAUTHORITY13/09/2025
Shammi Malhotra vs Ithaca Estates Private LimitedDirect opposite party to pay me the advance paid to them, loan disbursed amount,and clear all outstanding loan amount in my home loan acc no.LBBNG00003119183AUTHORITY13/09/2025
Avinash Kumar More and Nisha Agrawal vs Ithaca Estates Private LimitedRefund of Full Amount including the Pre-EMI reimbursementAUTHORITY13/08/2025
Mrs Delnaz Sam Dalal vs Ithaca Estates Private LimitedDirect the opposite party to pay me the advance paid,pre-emi,opportunity cost Rs.2/sft/PM, and clear outstanding in ICICI -loan No.LBMUM00003160401.AUTHORITY13/08/2025
Ghazlaa Parveen vs Ithaca Estates Private LimitedLooking for refund and compensationAUTHORITY12/07/2025
Arun Radhakrishnan pillai vs Ithaca Estates Private Limitedcancellation & refund of entire amount along with Opportunity cost & Interest as per RERAAUTHORITY12/07/2025
Dr Sanjay Kumar Misra vs Ithaca Estates Private Limiteda. Grant the Complainants the leave to exit the project b. Refund of sum of Rs. 8,49,526/- at 18% interest c. Direct the Respondents to clear/ discharge the loan amount received by them & OCAUTHORITY12/07/2025
Joyson Simon Raymond Furtado vs Ithaca Estates Private LimitedRefund of the amount as per below schedule along with interest.AUTHORITY11/07/2026
Chris Mathew vs Ithaca Estates Private LimitedRefund of the amount as per below schedule along with interest.AUTHORITY11/07/2026
Vishnupriya vs Ithaca Estates Private LimitedTransfer of loan to the builder through InjunctionAUTHORITY08/06/2023
Ashmeet Singh Chhabra vs SKYLARK ITHACAa. Grant the Complainants the leave to exit the project 2.Direct Respondents to refund the sum of Rs. 59,27,646 along with 18% interest and direct respondent to clear loan amount 3. Opportunity costAUTHORITY08/03/2025
Ayz Ali Cheriya Melat vs Ithaca Estates Pvt LtdKindly get my money refunded as project stalled since 2017, Rs. 30,29,520/- plus interest and compensation for mental harrassment, stress and tension.AUTHORITY08/03/2025
NITIN PURI vs M/S.ITHACA ESTATESIt is praid to kind authority of Karnataka RERA , Bengaluru to kindly order against the respondent / promoter for refund of the monies of the complainant for Rs. 6132527 with interestsAUTHORITY06/08/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (141 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190208/0002078
08-02-2019
compensation for delay in emi creditSkylark IthacaDISPOSED AO
CMP/190211/0002081
11-02-2019
Refund of booking amount upon cancellationSkylark IthacaDISPOSED AO
CMP/190212/0002122
12-02-2019
Pre emi reversal and exit option apply as per the aggrementSkylark IthacaDISPOSED AO
CMP/190228/0002141
28-02-2019
Delay in Construction of Skylark IthacaSkylark IthacaDISPOSED AO
CMP/190216/0002145
16-02-2019
The claim is for refund and compensation with interest at the rate of SBI Basic Prime lending rate plus 2percent from the date of payment to till the date of realization.Skylark IthacaDISPOSED AO
CMP/190217/0002176
17-02-2019
Exit Option, Amount Repayment and Cancellation of RERA RegistrationSkylark IthacaDISPOSED AO
CMP/190219/0002217
19-02-2019
Delay in possession & halted constructionSkylark IthacaDISPOSED AO
CMP/190219/0002218
19-02-2019
Delay in Possession and no work progressSkylark IthacaDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved29-11-2013BWSSB 291113.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved12-03-2014KSPCB 120314.pdf
KSPCB- MOEF (Above 50 Acres)Approved04-07-2015MOEF 040715.pdf
KPTCL- BESCOMApproved19-04-2025BESCOM 190425.pdf
Fire and SafetyApproved25-01-2014Fire 250114.PDF
Airport Authority of IndiaApproved09-03-2013Airport 090313.pdf
BSNL/Telecommunication DepartmentApproved24-02-2014BSNL 2402014.pdf

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress34% → 34% (+0 pts)
Units sold/booked as registered998/1761 (57%)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹42.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank Commissariat Road (IFSC ICIC0000002, a/c …4745). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub5 km
Bellandur–Marathahalli belt10 km
Outer Ring Road / Manyata13 km
MG Road / city centre14 km
Electronic City20 km
Kempegowda Int'l Airport21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Ithaca Estates.

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.