Bangalore/Project record

K-RERA · the public record

Sound of Water Phase 3

Bengaluru North · Puravankara

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
95%construction reportedQ3 2025 filing
14units not bookedof 60 · Q3 2025 filing
30 Jun 2027declared completionK-RERA registration · read 26 Oct 2026

Free project details

Registration read 26 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

30 Jun 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 26 Oct 2026

Registered units and project size

3BHK
18
4BHK
3
3BHK
1
3BHK
1
3BHK
1
3BHK
6
3BHK
16
3BHK
14

Filed categories, unchanged · K-RERA registration · read 26 Oct 2026

The whole registration

5.1registered acres

11.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for Sound of Water Phase 3

K-RERA · PRM/KA/RERA/1251/309/PR/070622/004965

Project facts and comparisons

On the register

Declared completion30 June 2027
Land area20,454 sq m (5.1 acres)
Homes registered60
Tower/wing entries1
Unit mix57 × 3BHK, 3 × 4BHK

In context

Density11.9 homes per acre
Density in context7th percentile of 529 Bengaluru North projects (median 75.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units60Total inventory registered with K-RERA.
Official carpet area188,197 sqmTotal carpet area reported for the project.
Official built-up area15,593 sqmUseful scale context when comparing density and project cost.
Registered land area20,454 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~0.56Sanctioned floor-area ratio (≈11,415 sqm sanctioned FAR area ÷ 20,454 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)141Separate filed counts; these categories may overlap and are not added together.
Covered-parking field120Separate filed counts; these categories may overlap and are not added together.
Open-parking field21Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan number0173/14-15Use this to match the sanctioned drawing set shown by the builder.
Plan approval date10-11-2014
Project start date28-02-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3BHK1830%167 sqm
4BHK35%255 sqm
3BHK12%178 sqm
3BHK12%182 sqm
3BHK12%166 sqm
3BHK610%180 sqm
3BHK1627%178 sqm
3BHK1423%217 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Building 12-200601410 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 60 official flat/unit rows, matching the 60 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK57166.2-217.3 sqm0.4-0.5 sqm114
4 BHK3255.4 sqm0.6-0.7 sqm6

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Building 12-2060166.2-255.4 sqm0.4-0.7 sqm120
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
148Building 12-2004 BHK255.4 sqm0.7 sqm2
149Building 12-2003 BHK217.3 sqm0.5 sqm2
150Building 12-2003 BHK217.3 sqm0.5 sqm2
151Building 12-2003 BHK166.9 sqm0.4 sqm2
152Building 12-2003 BHK166.9 sqm0.4 sqm2
153Building 12-2003 BHK166.9 sqm0.4 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

All 44 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Complaints on this project's K-RERA page (53 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190321/0002481
21-03-2019
Refund of 2lac rupees token amountProvident Park Square Phase - 1 (another project by this promoter)DISPOSED AO
CMP/190416/0002487
16-04-2019
Delay of flat delivery and Compensation as per Rera actPurva Westend Phase 1 (another project by this promoter)DISPOSED AO
CMP/190501/0002703
01-05-2019
Misguided ,Forced to pay 10% and with out SBI approval of Tower -not given Requested FlatProvident Park Square Phase - 1 (another project by this promoter)DISPOSED AO
CMP/190511/0002977
11-05-2019
NON REGISTRATION AND POSSESSION OF FLAT DELIVERY DATE EXPIREDPurva Sunflower (another project by this promoter)DISPOSED AO
CMP/190525/0003132
25-05-2019
Appeal for invoking section 18 of RERA Act for continuous delay in handover of apartmentPurva Westend Phase 1 (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/190611/0003274
11-06-2019
Builder is not responding to: cancellation of agreement by buyer due to delay in completionPurva Sunflower (another project by this promoter)DISPOSED AO
CMP/190618/0003322
18-06-2019
Booking amount refund 2 lakhsProvident Park Square 4 (another project by this promoter)DISPOSED AO
CMP/190714/0003570
14-07-2019
Complaint under Sec 18, Sec 31 & Sec 71 of the Real Estate (Regulation and Development) Act 2016, and under Rule 17, 29 & 30 of the Karnataka Real Estate (Regulation and Development) Rules 2017.Purva Palmbeach (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantV D S R & Co LLP001626S/S2000851968Bengaluru Urban, Karnataka - 560003
EngineerSatheesan A.MN/A0000Bengaluru Urban, Karnataka - 560042
ArchitectINDRAJIT SHARAD KEMBHAVIBCC/BL-3.6A-2569/2014-151977Bengaluru Urban, Karnataka - 560041
ContractorStarworth Infrastructure & Construction Limited-2009Bengaluru Urban, Karnataka - 560042

Builder track record

RERA filing

Puravankara has 30 other K-RERA-registered projects in our records (average reported construction progress 78%). 14 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹11.58 Cr collected from buyers, ₹8.14 Cr withdrawn from the project's escrow account.

Construction progress95% → 95% (+0 pts)
Units sold/booked as registered46/60 (77%)
Buyer collections in available QPRs₹11.58 Cr
Escrow withdrawals in available QPRs₹8.14 Cr (0.70x collections)
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹12 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹87.3 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: ICICI Bank M G ROAD IFSC Code : ICIC0000002 Pin Code : 560025. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 6 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City6 km
Bellandur–Marathahalli belt13 km
MG Road / city centre14 km
Whitefield IT hub21 km
Outer Ring Road / Manyata21 km
Kempegowda Int'l Airport40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Puravankara. View Puravankara's full track record →
Puravankara has 31 projects registered in Bangalore, 6 completed, 1 past RERA deadline.
2 complaints on the K-RERA register against Puravankara in Bangalore.

Buyer reviews · MouthShut

★★☆☆☆ 1.52/5

663 reviews for Puravankara in Bangalore
Read 663 reviews on MouthShut →

Other projects by this builder in Bangalore

Provident Park Square 5
Past deadline · 91% built · 99% sold
Provident Deansgate
Filing overdue · 76% built · 88% sold
Provident Deansgate Phase 2
Filing overdue · 24% built · 60% sold
Purva Blubelle
Filing overdue · 35% built · 89% sold
Purva Oakshire
Filing overdue · 100% built
Purva Orient Grand
Filing overdue · 51% built · 11% sold

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 26 Oct 2026. Document and inventory dates are shown in their sections.