Bangalore/Project record

K-RERA · the public record

THE GREEN BELT

Bengaluru North · Bharath Subbarao

Project X-Ray · for this project

Before you book, see what you’re really buying.

The layout. The real costs. The commitments. We read the plans and filings together, so you can decide with a clearer picture.

Six checks for your project.

  1. The Family Fit Scan

    A large plot can still leave little room to build. We read the layout, access and building restrictions before you choose.

  2. The Premium Lens

    A corner or park-facing plot can cost more. See what its position, roads and nearby phases actually offer.

  3. The Unwritten Bill

    The plot price may leave out utility connections and shared maintenance. We flag the commitments in the filed terms.

  4. The Neighbour Math

    A park beside your plot may serve several phases. We check shared access, facilities and neighbouring uses.

  5. The Progress Pulse

    A marked plot is not the same as a serviced one. We check the filed progress of roads, water and power.

  6. The Lawyer’s Shortlist

    A small token can come with a much larger cancellation charge. We flag that, the seller’s authority and documents your lawyer should check.

See the report before you buy

See the findings, not just a list of checks.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project X-Ray sample ↗
30 Sep 2019declared completionK-RERA registration · read 05 Nov 2026

Free project details

Registration read 05 Nov 2026

Registered units and project size

Plots-Residential layout
98

Filed categories, unchanged · K-RERA registration · read 05 Nov 2026

The whole registration

6.6registered acres

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for THE GREEN BELT

K-RERA · PRM/KA/RERA/1251/309/PR/180507/001665

Project facts and comparisons

On the register

Declared completion30 September 2019
Land area26,911 sq m (6.6 acres)
Unit mix98 × Plots-Residential layout

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered land area26,911 sqmThe land area attached to this K-RERA registration.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-04-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Plots-Residential layout98100%0 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

3 of 18 compliance document slots are filed as Not Applicable; the remaining 15 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Sep 2019, extended (Extension) to 30 Jun 2023 — both dates have passed with no OC on file. The extension on file was granted on 18 Feb 2020 (K-RERA extension no. EX/PRM/KA/RERA/1251/309/PR/200218/001665) — it has been used, its deadline has also passed, and no further extension is recorded.

Approval documents

Electricity (BESCOM/ESCOM)Not identified in the document list
Water & sewage (BWSSB/KWSSB)Not identified in the document list
Fire NOCNot identified in the document list
Pollution control (KSPCB)Not identified in the document list
Environmental clearanceNot identified in the document list
Airport Authority height clearanceNot identified in the document list

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/210804/0008210
04-08-2021
Refund with InterestTHE GREEN BELTDISPOSED AUTHORITY BENCH6
CMP/210805/0008211
05-08-2021
Delivery Date ExpiryTHE GREEN BELTDISPOSED AUTHORITY FULLBENCH
CMP/211201/0008658
01-12-2021
The project delayed by more than 2 yearsTHE GREEN BELTDISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectKomathi P-20077th Cross, K.R.Puram
ContractorEncien Engineering and Construction Pvt Ltd-2017Ulsoor Road, Bangalore
Structural engineerRajesh Consultants---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Axis Bank Sadashiv Nagar Branch (IFSC UTIB0001887, a/c …6561). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 3 project-photo uploads.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest of the listed job hubs is about 10 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre3 km
Outer Ring Road / Manyata10 km
Bellandur–Marathahalli belt12 km
Electronic City16 km
Whitefield IT hub19 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bharath Subbarao.
3 complaints on the K-RERA register against Bharath Subbarao in Bangalore.

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 5 Nov 2026. Document and inventory dates are shown in their sections.