Bsr Developers has 5 RERA-registered projects: 2 projects past declared completion date. All figures are the developer's own regulator filings.

2
Past declared date

Public registration records

These records have not been classified as delivered, under construction or overdue. The declared date and status are filings, not a current site inspection.

BSR ISLAND

Hyderabad region · Registered: 2019-06-13 · Declared completion: 2021-06-28

BSR CENTRAL

Hyderabad region · Registered: 2021-02-23 · Declared completion: 2023-12-29

Considering a specific Bsr Developers project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (2)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
AKRUTHI GREEN WOODSBengaluru2020-04
BSR THAPOVANABengaluru2025-07
Registered, no progress filed yet (1)click to expand
ProjectCity
SUN SHINEBengaluru

Figures are Bsr Developers's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.