Developer RERA record

Imperia

Imperia has 15 RERA-registered projects: strong Gurugram delivery record (3/3 projects with OC); 2 projects under construction, Bengaluru averaging 84% construction; 6 projects past their declared completion date. All figures are the developer's own regulator filings.

Flagged
Delivery signal
2
Under construction
3
Completed / delivered
6
Past declared date
98%
Bengaluru inventory booked
11
RERA complaints filed

Under construction

Under construction — 2 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
Assetz Soho & SkyBengaluru91%
Assetz Soho & Sky Phase 1BBengaluru78%
Considering a specific Imperia project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (3)click to expand
ProjectCityStatus
ESFERA, PHASE-IIGurugramOC issued
IMPERIA SHOPPING CENTRALGurugramOC issued
MINDSPACEGurugramOC issued
Past declared date (6)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
MIRAGE PHASE INoida2021-09
MIRAGE PHASE IINoida2025-06
PREMERIANoida2018-12
CYBERNoida2019-12
BANDHANNoida1900-01
WORLD OF TASTENoida2020-09
Registered, no progress filed yet (4)click to expand
ProjectCity
MONTECITOBengaluru
THE SEPHYRANoida
PRIDEVILLENoida
TAIF RESIDENCYBengaluru

RERA complaints & orders

Regulatory record

11 total complaints filed — above average for builders we track (68th percentile).

10
MahaRERA complaints
1
Karnataka RERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Imperia's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.