Developer RERA record

Lakepoint Builders

Lakepoint Builders has 8 RERA-registered projects: 8 projects past their declared completion date. All figures are the developer's own regulator filings.

Flagged
Delivery signal
8
Past declared date
1
RERA complaints filed
Considering a specific Lakepoint Builders project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (8)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Devanahalli Phase 1A PlotsBengaluru2019-08
Devanahalli Phase II PlotsBengaluru2023-01
Devanahalli Phase 1 PlotsBengaluru2021-03
Clover VillaBengaluru2022-11
Villa Phase 1CBengaluru2022-05
Villa Phase 1ABengaluru2021-12
Building No 9,10,11,12 and 13Bengaluru2019-04
Building Nos. 8,9 (part), 28, 29Bengaluru2019-04

RERA complaints & orders

Regulatory record

1 total complaints filed — below average for builders of this scale (23th percentile).

1
Karnataka RERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Lakepoint Builders's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.