Developer RERA record

Rustomjee

Rustomjee has 37 RERA-registered projects: 29 projects under construction; 8 projects past their declared completion date. All figures are the developer's own regulator filings.

On the register
Delivery signal
29
Under construction
8
Past declared date

Under construction

Under construction — 29 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
Rustomjee 180 Bayview Matunga W - Wing AMumbaipossession by Dec 2029
Rustomjee 180 Bayview Matunga W - Wing BMumbaipossession by Jun 2029
Rustomjee AdenMumbaipossession by Dec 2026
Rustomjee AshianaMumbaipossession by Feb 2027
Rustomjee Balmoral - Wing AMumbaipossession by Apr 2030
Rustomjee Balmoral - Wing CMumbaipossession by Dec 2030
Rustomjee Balmoral - Wing DMumbaipossession by Apr 2030
Rustomjee Balmoral - Wing FMumbaipossession by Apr 2030
Rustomjee Belle VUEMumbaipossession by Dec 2027
Rustomjee CleonMumbaipossession by Jun 2027
Rustomjee Cliff TowerMumbaipossession by Oct 2030
Rustomjee CrescentMumbaipossession by Dec 2029
Rustomjee LA Familia - Wing AMumbaipossession by Dec 2026
Rustomjee LA Familia- Wing CMumbaipossession by Jun 2027
Rustomjee LA VIE Wing AMumbaipossession by Dec 2028
Rustomjee LA VIE Wing CMumbaipossession by Feb 2029
Rustomjee LA VIE Wing DMumbaipossession by Jul 2031
Rustomjee Ocean VistaMumbaipossession by May 2029
Rustomjee PriveMumbaipossession by Nov 2029
Rustomjee StellaMumbaipossession by Dec 2027
Rustomjee Urban Woods - BanyanMumbaipossession by Jun 2030
Rustomjee Urban Woods - MapleMumbaipossession by May 2029
Rustomjee Urban Woods - OakMumbaipossession by Apr 2029
Rustomjee Urban Woods - PalmMumbaipossession by May 2029
Rustomjee Urban Woods - WalnutMumbaipossession by Apr 2029
Rustomjee Urban Woods - Wing AMumbaipossession by Mar 2028
Rustomjee Verdant Vistas Wing AMumbaipossession by Jan 2030
Rustomjee Verdant Vistas Wing BMumbaipossession by Feb 2030
Rustomjee Vista BayMumbaipossession by Jan 2031
Considering a specific Rustomjee project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (8)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Rustomjee Azziano Wing DMumbai2025-03
Rustomjee Azziano Wing LMumbai2025-03
Rustomjee Crown -Phase IIMumbai2026-06
Rustomjee Paramount - Wing CMumbai2022-06
Rustomjee Paramount - Wing FMumbai2025-12
Rustomjee ReserveMumbai2025-12
Rustomjee Seasons - Wing DMumbai2025-12
Rustomjee SummitMumbai2024-12

Figures are Rustomjee's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.