Developer RERA record

Vilas Javdekar

Vilas Javdekar has 30 RERA-registered projects: 19 projects under construction; 11 projects past their declared completion date — a significant track-record flag. All figures are the developer's own regulator filings.

On the register
Delivery signal
19
Under construction
11
Past declared date

Under construction

Under construction — 19 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
38K Inclusive HousingPunepossession by Dec 2026
Palladio Balewadi Central Phase 1Punepossession by Dec 2027
Palladio Balewadi Central Phase 2Punepossession by Dec 2028
Palladio Kharadi CentralPunepossession by Jun 2027
Palladio Kharadi Central Phase 2Punepossession by Dec 2028
Palladio LavientoPunepossession by Dec 2029
Palladio Presidential Suites Balewadi RiverfrontPunepossession by Dec 2032
Portia GrandePunepossession by Dec 2027
Pratik Nagar Palladio Kothrud CentralPunepossession by Dec 2030
Uk1321 Inclusive HousingPunepossession by Dec 2026
VJ Central AvenuePunepossession by Dec 2026
VJ Indilife KharadiPunepossession by Dec 2028
VJ Indilife WakadPunepossession by Jun 2027
VJ Indiworks Kharadi CentralPunepossession by Dec 2029
Yashone Eternitee Phase 2Punepossession by Jun 2027
Yashwin Enchante Phase 1Punepossession by Jun 2027
Yashwin Enchante Phase 2Punepossession by Dec 2029
Yashwin Urbo Centro - Phase 1Punepossession by Dec 2027
Yashwin Urbo Centro Phase 2Punepossession by Jun 2029
Considering a specific Vilas Javdekar project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (11)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
172W Inclusive HousingPune2026-06
51B Inclusive HousingPune2025-12
Palladio Phase 2Pune2022-12
Yashone Eternitee Phase 1Pune2026-04
Yashone Infinitee - Phase IIPune2025-12
Yashone Infinitee - Phase IIIPune2025-12
Yashwin HinjawadiPune2025-06
Yashwin NuovocentroPune2026-06
Yashwin Orizzonte - Phase IPune2024-06
Yashwin Orizzonte Phase IIPune2025-12
Yashwin SupernovaPune2026-03

Figures are Vilas Javdekar's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.