Mumbai/Project record

MahaRERA · the public record

Aashray

Boriwali (W), Babhai Naka · Vintage Enterprises

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2022declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for Aashray

MahaRERA · P51800019496

Delivery and registration

When is the project declared for completion?

Aashray is registered with MahaRERA as P51800019496 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

46months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP51800019496
Registered on06 Feb 2019
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Aashray in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Aashray1G+11-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Aashray, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 19 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000030296921/10/2022Deepak Kumar vs M/s. Vintage Enterprisesorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2021DUE TO APPALLING MARKET CONDITIONS AND NON TIMELY ARRANGEMENT OF FUNDS AND CLEARANCE OF DCR NORMS PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD REQUEST YOU TO KINDLY GRAN
30 Mar 202131 Dec 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2022

Location, Land & Connectivity

Located at Boriwali (W), Babhai Naka, LT Road, Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by By FP No- 320, to the south by By CTS No-162 and DP Road, to the east by By CTS No-163 and DP Road and to the west by By FP No- 320. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Navkar Palazzo
Not filing quarterly progress reports · declared completion Dec 2026 · Navkar Infra Projects
THE Zone
declared completion Dec 2026 · MS Amann RAJ Housing AND Development Cor
9 Rajgir
declared completion Dec 2026 · M S Kavita Construction Company
Adarsh Garden Grove
declared completion Dec 2026 · Adarsh Enterprises
Akshaya AND Jayshree Redevelopment
declared completion Dec 2026 · NHI Developers LLP
Atulya
declared completion Dec 2026 · Phoenix Developers
More builders in Borivali West

Major developers building in Borivali West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Aashray
declared completion Dec 2027 · Creative Builders
Aatman
declared completion Oct 2028 · Gurukrupa Realcon Builders AND Developer
Aatmay
declared completion Dec 2028 · APV Developers
Aavaas Classic
declared completion Mar 2022 · M. K. Realtors
Aayush Aurum
declared completion Sep 2028 · Aayush Builders & Developers LLP
Aayush Ayaansh
declared completion Dec 2025 · Aayush Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.