Mumbai/Project record

MahaRERA · the public record

AASTHA HEIGHTS

Shivaji PArk · AASTHA ASSOCIATES

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Mar 2020declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for AASTHA HEIGHTS

MahaRERA · P51900016659

Delivery and registration

When is the project declared for completion?

AASTHA HEIGHTS is registered with MahaRERA as P51900016659 and the promoter has declared completion for 30 Mar 2020.

30 Mar 2020

declared completion

79months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51900016659
Registered on05 Jun 2018
Promoter-declared completion30 Mar 2020
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AASTHA HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AASTHA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
AASTHA HEIGHTS1G+18-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for AASTHA HEIGHTS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007924410/05/2019Nandini Shenoy & Vinayak Shenoy vs M/s Aastha Associatesorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2020Though our Project is of 19 Floors, we have received CC only up to 16th Floor. We are in the process of procuring the CC for the remaining floors. Since we have not received the CC

Location, Land & Connectivity

Located at Shivaji PArk, Ranade Road, Ward GNorth, Mumbai City, 400019. Per the filed land record, the plot is bounded to the north by 731 B 10, to the south by 17 B 10, to the east by 731 C10 and to the west by R P MASANI ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Matunga

Chhaya
declared completion Dec 2026 · Fortune Realty
Jade Acharya
declared completion Dec 2026 · Raghavendra Acharya & Others
Shayona
declared completion Dec 2026 · Devesh Narendra Jani
Jade Solitaire
declared completion Mar 2027 · National Happy Homes
Bellwether Amari
declared completion Jun 2027 · Bellwether Infrastructure LLP
Amrut Villa
declared completion Oct 2027 · Pyramid Realty
More builders in Matunga

Major developers building in Matunga

More projects in Mumbai City

Other RERA-registered projects in Mumbai City

Aayesha Palace
declared completion Dec 2027 · Zoeb Enterprises
Adarsh Nagar Vikas CHS
declared completion Feb 2022 · Firoz Usmantinwala
Adi Darsshan
declared completion Dec 2026 · Adi Realtors
Aditya Highrise Project
declared completion Dec 2021 · Anil Ramrao Naik
Adityaraj Midtown
declared completion Jun 2028 · Kent Corporation
Adobe Heights
declared completion Dec 2021 · Siddhi Enclave

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.