ARADHYA RESIDENCY

KELWA · DEVINE INFRA

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Mar 2027declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for ARADHYA RESIDENCY

MahaRERA · P99000026640

Delivery and registration

When is the project declared for completion?

ARADHYA RESIDENCY is registered with MahaRERA as P99000026640 and the promoter has declared completion for 31 Mar 2027.

31 Mar 2027

declared completion

5months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000026640
Registered on12 Oct 2020
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today5 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ARADHYA RESIDENCY record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ARADHYA RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
WING A1G+331 Mar 2021
WING B1G+331 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2027DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/03/2027

Location, Land & Connectivity

Located at KELWA, PATIL PADA, Borivali, Mumbai Suburban, 401401. Per the filed land record, the plot is bounded to the north by PLOT NO 11, to the south by PLOT NO 7, to the east by GUT NO 40 B PART and to the west by 6 M WIDE LAYOUT ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kelve Road

Karrm Brahmaand Affordable Homes PVT LTD
Not filing quarterly progress reports · declared completion Dec 2026 · Karrm Brahmaand Affordable Homes Private
Bhaskar Save Nagar
declared completion Dec 2026 · Sai Builders And Developers
Rose Heights
declared completion Dec 2026 · Mehandi Hasan Sarif Shalmani
Savera Complex
Not filing quarterly progress reports · declared completion Dec 2026 · Savera Builders & Developers
THE Hill Touch
declared completion Dec 2026 · Aristone Infra
SK Swarnik Homes
declared completion Feb 2027 · SK Swarnik Homes
More projects in Palghar

Other RERA-registered projects in Palghar

Arafat CHS Ltd,anab CHS Ltd, AL Ashiyana CHS LTD
declared completion Dec 2027 · Karari Group Builders & Developers
Arch Developers
declared completion Mar 2027 · Arch Developers
Arham Villas
declared completion Mar 2022 · Vasudha Builders Limited
Ariana
declared completion Mar 2027 · Mansarovar Estate Builders LLP
Arihant Associates Developers
declared completion Dec 2029 · Arihant Associates Developers
Arihant Residency
declared completion Jun 2025 · Sheetal Construction

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.