Mumbai/Project record

MahaRERA · the public record

ARIHANT ANMOL PHASE II

Badlapur · ARIHANT VATIKA REALTY PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Mar 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for ARIHANT ANMOL PHASE II

MahaRERA · P51700003112

Delivery and registration

When is the project declared for completion?

ARIHANT ANMOL PHASE II is registered with MahaRERA as P51700003112 and the promoter has declared completion for 30 Mar 2022.

30 Mar 2022

declared completion

55months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700003112
Registered on04 Aug 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Promoter record

What else is this promoter on record for?

ARIHANT VATIKA REALTY PRIVATE LIMITED is the promoter of record on 9 projects registered with MahaRERA.

9projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ARIHANT ANMOL PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
B11G+1230 Mar 2020
B21G+1230 Mar 2020
B31G+1130 Mar 2020

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for ARIHANT ANMOL PHASE II, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007859923/03/2019GANESH KRISHNAN vs ARIHANT VATIKA REALTY PRIVATE LIMITEDorder passed
CC00600000019543931/12/2020Neelofer Abhijeet Pattebahadur vs ARIHANT VATIKA REALTY PRIVATE LIMITEDorder passed
CC00600000025188817/07/2022HENRY DOUGLAS ANTHONY vs Arihant Vatika Realty Pvt. Ltd.order passed
SM1260028727/04/2026Bhakti Achrekar vs ARIHANT VATIKA REALTY PRIVATE LIMITEDorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Filed descriptions (status fields empty): 1 “NOTICE UNREADY”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Senior Division KalyanSPECIAL CIVIL SUIT NO-360 OF 20122012Status not supplied
Filed description: NOTICE UNREADY

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2021The construction of the said project has been completed on 15th September, 2020 and we have received the Completion certificate issued by Mr. Satish Kanade, Architect dated 15th S

Location, Land & Connectivity

Located at Badlapur, Badlapur, Thane, Thane, 421503. Per the filed land record, the plot is bounded to the north by SURVEY NO - 67-6-3, to the south by SURVEY NO - 67 PART, to the east by SURVEY NO - 67 PART and to the west by SURVEY NO - 69 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 36 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park36 km
Andheri MIDC / SEEPZ39 km
Chhatrapati Shivaji Int'l Airport40 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district46 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Arihant Vatika Realty Private Limited project & its RERA track record →

Other RERA-registered projects in Badlapur

Aarya Prem CO-OP HSG SOC
declared completion Oct 2026 · K S Builders & Developers
Vishnu Vatika NX Phase II D & H Wing
declared completion Oct 2026 · M/s. Vishnu Group
JAY Ramdarshan CHS LTD
declared completion Nov 2026 · Mitra Buildcon
SAI Darshan
declared completion Nov 2026 · SAI Krupa Builders
Vastu Rachana
declared completion Dec 2026 · Gagangiri Infra
Prabhu Darshan CO-Operative Housing Society Limited
declared completion Dec 2026 · NYP Developers
More builders in Badlapur

Major developers building in Badlapur

More projects in Thane

Other RERA-registered projects in Thane

Arihant Anmol Phase III
declared completion Jun 2026 · Arihant Vatika Realty Private Limited
Arihant Anmol Phase V
declared completion Dec 2028 · Arihant Vatika Realty Private Limited
Arihant Avanti
declared completion Dec 2031 · Arihant Superstructures Limited
Arihant Avanti Phase II
declared completion Dec 2031 · Arihant Superstructures Limited
Arihant City Phase-II - A Building
declared completion Dec 2026 · Arihant Enterprises
Arihant City Phase-II - B Building
declared completion Dec 2026 · Arihant Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.