Mumbai/Project record

MahaRERA · the public record

Athena

Goregaon West · M/s. Sahajanand Developers

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Jan 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Athena

MahaRERA · P51800003330

Delivery and registration

When is the project declared for completion?

Athena is registered with MahaRERA as P51800003330 and the promoter has declared completion for 31 Jan 2024.

31 Jan 2024

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800003330
Registered on05 Aug 2017
Promoter-declared completion31 Jan 2024
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Athena in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
Athena1G+2331 Mar 2020

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for Athena, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007881809/04/2019PRITI VIJAY DODHIA vs Sahajanand Developersorder passed
CC00600000025192114/07/2022Vaibhav Gawde vs M/s Sahajanand Developersorder passed
CC00600000026208226/07/2022Richad Tahora vs Sahajanand Developersorder passed
CC00600000029221604/08/2022Mahesh M Kotian vs Sahajanand Developersorder passed
CC00600000039738307/09/2023Sushila Lalji Kurmi vs Sahajanand Developersorder passed
CC00600000059121019/07/2024AARTI SURESH CHANDWANI vs Sahajanand Developersorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2021Delay due to change in approval authority
31 Mar 202130 Jun 2022Due to various lockdowns because of COVID 19, the availability of labour and materials is less which is affecting the construction schedule.
30 Jun 202231 Jan 2024The main reason for stalling of project was the health of the promoter. He has faced multiple operations and therapy before resuming in office. The members of the erstwhile society

Location, Land & Connectivity

Located at Goregaon West, S.V.Road, Borivali, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by By open space and MHADA Bldg, to the south by By Road and Bldg No 6, to the east by By S V Road and to the west by By open space and bldg of Gurukul CHS Ltd. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park7 km
Chhatrapati Shivaji Int'l Airport7 km
Bandra Kurla Complex (BKC)10 km
Lower Parel / Worli business district17 km
Nariman Point / Fort25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon West

Vallabh Krupa Chsl
declared completion Oct 2026 · Gun Rajan Constructions
Siddharth Nagar Gulmohar CHS LTD
declared completion Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Paschim Jagruti CHS LTD
declared completion Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Swami Vivekanand Chsl
declared completion Dec 2026 · Dhariwal Developers Private Limited
Asmi Legacy
declared completion Dec 2026 · Asmi Developers
Building No.9 - Phase II
declared completion Dec 2026 · Kalindi Estate Developers
More builders in Goregaon West

Major developers building in Goregaon West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Athena
declared completion Aug 2027 · Astrum Developers
Atlanta Heights - 15th To 18th Floor
declared completion Feb 2026 · Rare Townships Private Limited
Atlanta Heights - 19th Floor
declared completion Jun 2026 · Rare Townships Private Limited
Atlanta Heights - Upto 14th Floor
declared completion Jun 2026 · Rare Townships Private Limited
Atlantis
declared completion Dec 2027 · NHP Construction LLP
Atlantis
declared completion Dec 2033 · Goldeneon Developers Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.