Project RERA record · Mumbai, Thane & the MMR

Atlanta Estate Extension

by Atul Raj Builders Pvt Ltd · MahaRERA P51900003990 · Certificate Signed · declared completion Mar 2028

Not filing quarterly progress reports

Not filing quarterly progress reports. Mumbai City

Not filing quarterly progress reports

The developer is not filing the legally required quarterly progress reports with MahaRERA. This is a compliance violation and makes it impossible to independently track construction progress through the regulator.

Atlanta Estate Extension is on MahaRERA's non-compliance list for not filing quarterly progress reports. RERA requires developers to report construction progress and sales data to the regulator each quarter — the absence of filings means construction status cannot be independently verified through MahaRERA's public register.

On the regulator's record

  • 37 quarterly reporting periods on MahaRERA's compliance schedule — 37 flagged for QPR default, currently in default on QPR filings
  • 2 litigation cases on MahaRERA's record for this project

Source: MahaRERA public project record.

Other RERA-registered projects in Goregaon East

Aasamanta Laxmi Narayan
Aasamanta Realty
Aasamanta White House
Aasamanta Realty
Accord Classic
Suyojana Impex Pvt. LTD
Adinarayan Co-Op Hsg. Society Ltd
Navnath Majestic Infra LLP
Aether Wing B2 - Phase 1A - Upto 20th Floor
Romell Properties Private Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Request the report on Atlanta Estate Extension

We analyse Atlanta Estate Extension in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Free · Risk Snapshot + alerts

The regulatory risk spine for Atlanta Estate Extension, emailed as a clean scorecard — plus an alert if the RERA status changes:

  • 🔴  Not filing quarterly progress reports

Something went wrong — email hello@quietlist.in.

✓ On its way to your inbox — plus alerts if the status changes.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Jul 2026