AZAD RESIDENCY

Byculla · DUDHWALA CONSTRUCTION

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

0units filed as unsoldInventory · 19 October 2026
30 Jun 2026declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for AZAD RESIDENCY

MahaRERA · P51900011568

Delivery and registration

When is the project declared for completion?

AZAD RESIDENCY is registered with MahaRERA as P51900011568 and the promoter has declared completion for 30 Jun 2026.

30 Jun 2026

declared completion

4months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51900011568
Registered on31 Aug 2017
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AZAD RESIDENCY record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In AZAD RESIDENCY, ₹15.62 Cr of a declared ₹16.73 Cr estimated project cost is reported as incurred, about 93.4%, as at the last certified filing with MahaRERA.

93.4%

₹15.62 Cr

of ₹16.73 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 18 Jul 2026

What the filings record, unit by unit

Read from MahaRERA on 19 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 34 units carry one, and Every unit on the filing is recorded sold or booked.

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet.

This snapshot marks all units in AZAD RESIDENCY as sold or booked. It does not establish current availability. The filed values can still help you compare a quote. The Sales Report lists the 34 sold or booked entries with filed values: each unit, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 34 filed sold/booked entries — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
AZAD RESIDENCY1G+2430 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2026The OC for the 22nd and 23rd floors is currently pending due to certain approvals that are still under process.Therefore, we kindly request additional time to complete the pending

Location, Land & Connectivity

Located at Byculla, MEGHRAJ SETHI MARG, Ward E, Mumbai City, 400008. Per the filed land record, the plot is bounded to the north by MEGHRAJ SETHI MARG, to the south by 11 - 1840, to the east by 1840 PT and to the west by MAULANA AZAD ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 3 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Nariman Point / Fort5 km
Bandra Kurla Complex (BKC)11 km
Chhatrapati Shivaji Int'l Airport13 km
Andheri MIDC / SEEPZ18 km
Powai / Hiranandani business park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Byculla

Shelaji Avenues
declared completion Dec 2026 · Ashirwad Shelaji Developers LLP
Baug E Umar
declared completion Dec 2026 · Mahanagar Constructions Private Limited
Golden Residency
declared completion Dec 2026 · Golden Realty
Nemat -E- Farooque Heritage
declared completion Dec 2026 · Falakdeveloper
White Flower Residency
declared completion Dec 2026 · White Flowers Realty LLP
Fatima Heights
declared completion Jan 2027 · M K Enterprises
More builders in Byculla

Major developers building in Byculla

More projects in Mumbai City

Other RERA-registered projects in Mumbai City

Azara Residences
declared completion Dec 2027 · Azara Redstone LLP
Bafna Horizon
declared completion Dec 2029 · JAS Realty
Bafna Pride
declared completion Dec 2030 · Navyug Enterprises
Bait US Salam
declared completion Dec 2028 · Y H Assoicates
Balaji Arcade
declared completion Dec 2026 · Shree Developers
Balaji Sharan
declared completion Oct 2021 · Haresh Pratap Chandan

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.