BAJAJ SAHIL

Thane · BAJAJ HABITAT PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for BAJAJ SAHIL

MahaRERA · P52000006897

Delivery and registration

When is the project declared for completion?

BAJAJ SAHIL is registered with MahaRERA as P52000006897 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000006897
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BAJAJ SAHIL record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BAJAJ SAHIL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
BAJAJ SAHIL A WING1G+8-

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for BAJAJ SAHIL, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000036469709/03/2023Mr. Chinmay Chakravarty and Mrs. Ragini Chakravarty vs M/S BAJAJ HABITAT PVT LTDorder passed
CC00600000039796704/11/2023MR RAJENDER BABU LINGAPURI AND MR SIVA SRINIVAS KOSANAM vs M/S BAJAJ HABITAT PVT LTDorder passed
CC00600000039796804/11/2023MR RAJENDER BABU LINGAPURI AND MR SIVA SRINIVAS KOSANAM vs M/S BAJAJ HABITAT PVT LTDorder passed
CC1250356907/10/2025Bidyadhar Shankarchandra Mandal vs BAJAJ HABITAT PRIVATE LIMITEDorder passed

Location, Land & Connectivity

Located at Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by CTS 290, to the south by CTS 390, to the east by 18 MTR ROAD and to the west by CTS 395 AND 399. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 51 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Nariman Point / Fort50 km
Bandra Kurla Complex (BKC)51 km
Powai / Hiranandani business park51 km
Lower Parel / Worli business district51 km
Chhatrapati Shivaji Int'l Airport53 km
Andheri MIDC / SEEPZ55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Shreeji Icon
declared completion Oct 2026 · Shreeji Lifespaces Group
Govind Ameya
declared completion Oct 2026 · Mansarovar Constructions
Shikara Greens Phase I
declared completion Oct 2026 · Shikara Constructions Pvt. Ltd.
Ambers Dnyaneshwar Capital
declared completion Nov 2026 · Capital Builders
Govind Greens
declared completion Nov 2026 · Priyal Buildcon LLP
Jupiter Royal
declared completion Nov 2026 · Arjun Ashok Tarachandani
More builders in Panvel

Major developers building in Panvel

More projects in Raigarh

Other RERA-registered projects in Raigarh

Balaji Aangan
declared completion Mar 2027 · Balaji Land Develoer
Balaji Archstone
declared completion May 2028 · Greystone Constructions
Balaji Avenue
declared completion Apr 2024 · Balaji Enterprises
Balaji Avvante - Building No. 11 And 12
declared completion Jun 2026 · Vishesh Greenscape LLP
Balaji Blossoms
declared completion Nov 2029 · Abhinav Buildwell
Balaji Complex - Plot NO 1 AND 2
declared completion Dec 2022 · Balaji Infra

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.