BKC EDGE

Dharavi · Labdhi Bliss Private Limited

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

125units filed as unsoldInventory · 22 October 2026
31 Dec 2029declared completionMahaRERA registration · read 18 Jul 2026
241registered unitsMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for BKC EDGE

MahaRERA · P51900013846

Delivery and registration

When is the project declared for completion?

BKC EDGE is registered with MahaRERA as P51900013846 and the promoter has declared completion for 31 Dec 2029.

31 Dec 2029

declared completion

38months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51900013846
Registered on27 Oct 2017
Promoter-declared completion31 Dec 2029
Current statusCertificate Signed
Against today38 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BKC EDGE record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In BKC EDGE, ₹16.72 Cr of a declared ₹258.57 Cr estimated project cost is reported as incurred, about 6.5%, as at the last certified filing with MahaRERA.

6.5%

₹16.72 Cr

of ₹258.57 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 18 Jul 2026

Sales

How many are filed as sold or booked?

In BKC EDGE, 89 of 214 units filed with MahaRERA are recorded as sold or booked (27 with registered agreements and 62 booked), about 42%, and 125 are filed as unsold.

42%sold or booked

89 of 214 units

₹134.44 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹28.47 Cr (about 21%) is recorded as collected and ₹105.98 Cr as receivable. The registration lists 241 units; this inventory lists 214. These are separate filed records. Their counts do not match; neither count establishes today's availability.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 89 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹22,079/sqft, with eight in ten falling between ₹8,668 and ₹41,114 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 27 owner/investor-held.

What the filings record, unit by unit

Read from MahaRERA on 22 October 2026

This unit list contains 241 entries; the separate sales summary contains 214. The lists can differ in status coverage and filing date. Use the source date shown with each.

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 89 units carry one, and 125 of the 241 are recorded unsold.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
Sale Building No 2-1513 (filed ID u1726234)522 sqftRs 1.24 cr typical, over Rs 45.04 lakh to Rs 8.60 cr
16 unusually low or high filed amounts are included in this range. Check the individual entries before using it to discuss a price.
53 filed · similar area (within 2%), elsewhere in project

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In BKC EDGE, 110 of the 125 unsold units have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 124 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20 and 241 units are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
Sale Building No 21G+20241-

Unit mix on the filing: 241 non-residential.

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for BKC EDGE, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005607224/10/2018Rekha Kunal Chheda vs Rajesh Unispaces Pvt Ltdorder passed
CC1260005104/01/2026MOHAMMAD NIZAMUDDIN SHAIKH vs savita patole labdhi blissorder passed

Legal & Litigation

The promoter has declared 10 court cases on this project to MahaRERA. Filed statuses: 7 “Closed”; 3 “Ongoing”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court26192015Closed
Filed description: Disposed
Bombay High Court22742017Ongoing
Filed description: Pre Admission
Bombay High Court22752017Ongoing
Filed description: Pre Admission
Bombay High Court22762017Ongoing
Filed description: Pre Admission
Grivance Redressal Committee Mumbai City32/20192019Closed
Filed description: Rejected
Grivance Redressal Committee Mumbai City33/20192019Closed
Filed description: The appeal is Rejected
Grivance Redressal Committee Mumbai City34/20192019Closed
Filed description: The appeal is Rejected
Grivance Redressal Committee Mumbai City35/20192019Closed
Filed description: The appeal is Rejected
Grivance Redressal Committee Mumbai City36/20192019Closed
Filed description: The appeal is Rejected
Bombay High Court2212020Closed
Filed description: Disposed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2029Initially, a Development Agreement was executed on 11th February 2011 between Rehab society and Sandeep Estate Development Private Limited. Subsequently, a Joint Development Agreem

Location, Land & Connectivity

Located at Dharavi, Dharavi, Ward GSouth, Mumbai City, 400017. Per the filed land record, the plot is bounded to the north by 72, to the south by 72, to the east by 19 and to the west by 19. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 2 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport5 km
Lower Parel / Worli business district6 km
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park9 km
Nariman Point / Fort14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dharavi

Bawa Aashiyaan Phase-II
declared completion Dec 2027 · KAY BEE Developers Pvt. Ltd.
CRD Aura
declared completion Dec 2027 · CRD Blue Ocean LLP
Bawa Aashiyaan Phase 1
declared completion Jun 2028 · KAY BEE Developers Pvt. Ltd.
F.w.tower
Not filing quarterly progress reports · declared completion Aug 2026 · Crystal Construction Corporation
Prince Tower
declared completion Jun 2025 · Punith Buildtech Private Limited
Samata B SRA CHS LTD
Past its declared completion date · declared completion Jun 2025 · Neeta Builders
More projects in Mumbai City

Other RERA-registered projects in Mumbai City

Bliss
declared completion Dec 2026 · M/s. Euphrosyne Infrastructure Pvt. Ltd
Blue Ocean
declared completion May 2027 · Quba Developers LLP
Bombay XI
declared completion Dec 2023 · Tattva & Mittal Lifespaces Pvt Ltd
Brahma Vihar
declared completion Dec 2017 · Unitex
Brand One Wadala - A Wing
declared completion Aug 2026 · AM Constructions
Brand One Wadala - B Wing
declared completion Aug 2026 · AM Constructions

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.