MahaRERA · the public record

CITY PRIDE

KATRAP · CITY PRIDE INCORPORATION

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for CITY PRIDE

MahaRERA · P51700017959

Delivery and registration

When is the project declared for completion?

CITY PRIDE is registered with MahaRERA as P51700017959 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

82months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700017959
Registered on01 Oct 2018
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 82 months past the declared date

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CITY PRIDE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A WING1G+431 Dec 2019
B WING1G+431 Dec 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for CITY PRIDE, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000043968817/03/2024GAURANG SUDHIR KADAM vs ANIKET SURESH GURAVorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 20201) As you know sir there is heavy downfall in the Real Estate Sector as well as economy as whole, that impacted the real estate sector, because of which we could not make out the s

Location, Land & Connectivity

Located at KATRAP, KATRAP CHOWK, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by ADJOINING PLOT NO 7, to the south by ADJOINING S NO26 H NO 1 P BANGLOW, to the east by ADJOINING 30 MT WIDE MIDC ROAD and to the west by ADJOINING S NO26 PLOT NO 26 AND LAYOUT GARDEN. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Aarya Prem CO-OP HSG SOC
declared completion Oct 2026 · K S Builders & Developers
Vishnu Vatika NX Phase II D & H Wing
declared completion Oct 2026 · M/s. Vishnu Group
JAY Ramdarshan CHS LTD
declared completion Nov 2026 · Mitra Buildcon
SAI Darshan
declared completion Nov 2026 · SAI Krupa Builders
Vastu Rachana
declared completion Dec 2026 · Gagangiri Infra
Prabhu Darshan CO-Operative Housing Society Limited
declared completion Dec 2026 · NYP Developers
More builders in Badlapur

Major developers building in Badlapur

More projects in Thane

Other RERA-registered projects in Thane

City Pride NX
declared completion Mar 2030 · Abhishek Buildcon
CKP Builder AND Developer
declared completion Dec 2029 · CKP Builder AND Developer
Classic Plaza
declared completion Dec 2028 · NEW Classic Construction
Classic Residency
declared completion Jun 2021 · Classic Construction
Code Name-Enchanted
declared completion Jun 2028 · Runwal Construction Private Limited
Codename Endgame – Tower 1
declared completion Dec 2034 · JP Infra Realty Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.