DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati

Mumbai Suburban · Surya-Landmark Developers Private Limited

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati

MahaRERA · P51800003226

Delivery and registration

When is the project declared for completion?

DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati is registered with MahaRERA as P51800003226 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

58months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800003226
Registered on05 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
DN NAGAR PANCHAVATI CO-OPERATIVE HOUSING SOCIETY LIMITED - GOKUL PANCHAVATI1G+1731 Dec 2019

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000067715/09/2017Ramji Sagan Satra vs Ms Surya Land Mark Developers Pvt Ltdorder passed
CC00600000011088812/09/2019Ravikiran Ashtaputre vs Mr. Murari Shahorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2020The project started in the year 2010 and within the period of one year completed 12 floors but the FSI got consumed.subsequently had to wait for 5 years to get the balance FSi and

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by Pratik CHS, to the south by 40Ft wide DP Road, to the east by MIDC Building and to the west by Jain Temple. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)6 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district13 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

ARC ONE
declared completion Dec 2026 · Chandra Gupta Estates Private Limited
MDM Maestro
declared completion Dec 2026 · MDM Realty LLP
Platinum Grandeur
declared completion Dec 2026 · Platinum Strategic Developers LLP
Tapodhan
declared completion Dec 2026 · Gurukul Realty LLP
Vengurlekars Chaitra
declared completion Dec 2026 · Vengurlekars Shreesai Builders And Devel
Gurukrupa Dhyanam
declared completion Mar 2027 · Gurukrupa Realcon Infrabuild LLP
More builders in Andheri West

Major developers building in Andheri West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Dollars Avenue Chsl
declared completion Nov 2027 · M/S Hirani Realtors
Dolphin Tower
declared completion May 2024 · Rajendra Builders Private Limited
Domain
declared completion Dec 2026 · M/s Build Square
Dosti ORO 67
declared completion Mar 2024 · KK Enterpises
Dotom Isle-Shakti
declared completion Jun 2025 · M/s. Dotom Real Estate
Dotom Jewel
declared completion Oct 2027 · Dotom Infraspace LLP

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.