Mumbai/Project record

MahaRERA · the public record

EKNATH ENCLAVE

Thane · Gauri Vinayak Builder and Developers Pvt Ltd

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for EKNATH ENCLAVE

MahaRERA · P51700010989

Delivery and registration

When is the project declared for completion?

EKNATH ENCLAVE is registered with MahaRERA as P51700010989 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

58months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700010989
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EKNATH ENCLAVE record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Gauri Vinayak Builder and Developers Pvt Ltd is the promoter of record on 13 projects registered with MahaRERA.

13projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for EKNATH ENCLAVE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
EKNATH ENCLAVE1G+830 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020We have applied for Extension due to delay on part of K.D.M.C in granting C.C ,resulting in overall delay & Suppliers of Materials(Steel,Cement) & Delay on Part of Labour Contracto

Location, Land & Connectivity

Located at Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by Janabai M Gaikwad, to the south by Prakash K Gaikwad, to the east by Dattu G Gaikwad and to the west by Janabai M Gaikwad. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 27 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park27 km
Andheri MIDC / SEEPZ29 km
Chhatrapati Shivaji Int'l Airport32 km
Bandra Kurla Complex (BKC)33 km
Lower Parel / Worli business district40 km
Nariman Point / Fort46 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Gauri Vinayak Builder And Developers Pvt Ltd project & its RERA track record →

Other RERA-registered projects in Kalyan East

Krishna Glory
declared completion Oct 2026 · Tulsi Kimaya Construction
Trimurti Garden
declared completion Dec 2026 · SAI Narayan Developers
Rai S Aaragya
declared completion Dec 2026 · RAI Residency Private Limited
Rai S Heaven
declared completion Dec 2026 · RAI Residency Private Limited
Ashwathi Heights
declared completion Dec 2026 · Prachiti Constructions
Barku Height
declared completion Dec 2026 · Shree Datta Developers
More builders in Kalyan East

Major developers building in Kalyan East

More projects in Thane

Other RERA-registered projects in Thane

Eknath Enclave Building NO 2
declared completion Dec 2023 · Gauri Vinayak Builder And Developers Pvt
Eknath Heights
declared completion Dec 2019 · Omkar Enterprises
Eknath Heights - 1
declared completion Dec 2022 · Omkar Enterprises
Ekopa CO OP Housing Society
declared completion Apr 2026 · Shrikrishna Ramchandra Marathe
Ekveera AAI Contruction
declared completion Apr 2025 · Ekveera AAI Construction
Ekveera Enterprises
declared completion Apr 2025 · Ekveera Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.