Gokul Silvermist

Santacruz (West) · Heena Builders and Developers

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
24 Jan 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Gokul Silvermist

MahaRERA · P51800012140

Delivery and registration

When is the project declared for completion?

Gokul Silvermist is registered with MahaRERA as P51800012140 and the promoter has declared completion for 24 Jan 2024.

24 Jan 2024

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800012140
Registered on01 Sep 2017
Promoter-declared completion24 Jan 2024
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Gokul Silvermist record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Gokul Silvermist in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Gokul Silvermist1G+830 Sep 2018

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for Gokul Silvermist, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007881909/04/2019LEENA K. NISAR & KIRAN N. NISAR vs HEENA BUILDERS & DEVELOPERSorder passed
CC00600000022097330/04/2022Vinod Padmakant Parekh vs M/s Heena Builders & Developersorder passed
CC00600000022103330/04/2022Vinod Padmakant Parekh vs M/s Heena Builders and Developersorder passed
CC00600000022103530/04/2022Vinod Padmakant Parekh vs M/s Heena Builders and Developersorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Our Project is located in the corridor area which is between the western railway and s.v road. Due to corridor Location the mcgm only permits SLUM TDR. Thus due to the scarcity of
30 Apr 202030 Apr 2020Due to change in policy DCPR 1991 TO 2034. The File is rejected twice due to changes in DCPR 2034 like “width of staircase.”(As per DCPR 2034 width of staircase is compulsory requi
30 Apr 202024 Jul 2023The TDR has been purchased for the said project but unable to move ahead because of the suit in the said project. Due to this force majeure situation we would please ask the author

Location, Land & Connectivity

Located at Santacruz (West), Junction of Beseant and Sai baba Road, Andheri, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by FPNO 15 TPS I, to the south by EXISTING SAIBABA ROAD, to the east by EXISTING BESANT ROAD and to the west by FP NO 17A TPS I. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district10 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz West

Woodstock Gardens
declared completion Oct 2026 · Woodstock Realties Private Limited
Artteza
declared completion Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · declared completion Dec 2026 · Shaista Majid Khan
Cyrilyn
declared completion Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
declared completion Dec 2026 · Shree Hari Realty
Orchid Vasundhara
declared completion Dec 2026 · Orchid Builtcon Pvt. Ltd.
More builders in Santacruz West

Major developers building in Santacruz West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Gokul Vaibhav
declared completion Sep 2020 · Heena Lifestyles
Gold Leaf
declared completion Dec 2029 · Shelaji Horizon LLP
Gold Residences
declared completion Mar 2029 · Time & Jet Realty LLP
Goldcrest Business Park
declared completion Dec 2018 · Swastik Associates
Golden Casa
declared completion Dec 2028 · Interlink Builders
Golden Heights @ Smgk Urbana
declared completion Aug 2025 · Smgk Developers Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.