88units filed as unsoldInventory · 25 October 2026
31 Dec 2030declared completionMahaRERA registration · read 19 Jul 2026
210registered unitsMahaRERA registration · read 19 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 19 Jul 2026

RERA details for IDBE CO OP HSG SOC LTD

MahaRERA · P99000052660

Delivery and registration

When is the project declared for completion?

IDBE CO OP HSG SOC LTD is registered with MahaRERA as P99000052660 and the promoter has declared completion for 31 Dec 2030.

31 Dec 2030

declared completion

50months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP99000052660
Registered on15 Sep 2023
Promoter-declared completion31 Dec 2030
Current statusCertificate Signed
Against today50 months to the declared date

Construction

How much construction cost has been reported?

In IDBE CO OP HSG SOC LTD, ₹6.84 Cr of a declared ₹25.00 Cr estimated project cost is reported as incurred, about 27.4%, as at the last certified filing with MahaRERA.

27.4%

₹6.84 Cr

of ₹25.00 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 19 Jul 2026

Sales

How many are filed as sold or booked?

In IDBE CO OP HSG SOC LTD, 3 of 103 units filed with MahaRERA are recorded as sold or booked, about 3%, and 100 are filed as unsold.

3%sold or booked

3 of 103 units

₹1.30 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹37.40 Lakh (about 29%) is recorded as collected and ₹93.01 Lakh as receivable. The registration lists 210 units; this inventory lists 103. These are separate filed records. Their counts do not match; neither count establishes today's availability.

Source · MahaRERA sold/unsold inventory filing · read 19 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, unit by unit

Read from MahaRERA on 25 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 15 units carry one, and 88 of the 103 are recorded unsold. Since we started watching this ledger, 12 units have moved out of the unsold list, most recently on 11 September 2026.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
A-1802574 sqftRs 8,243 a sq ft typical, over Rs 7,251 to Rs 13,554
1 unusually low or high filed amount is included in this range. Check the individual entries before using it to discuss a price.
5 filed · nearby areas in the project (within 8%)

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In IDBE CO OP HSG SOC LTD, 40 of the 88 unsold units have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 87 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15 and 210 units are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
IDBE CO OP HSG SOC LTD BUILDING NO 1 WING A AND B1G+1521031 Dec 2030

Unit mix on the filing: 165 residential and 45 non-residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NALLASOPARA WEST, S.No. 73 B/A , B/B of village Nilemore, Tal- Vasai, Dist- Palghar, Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by LODHA SHOPPING CENTER, to the south by MAIN ROAD, to the east by OPEN PLOT and to the west by SATKAR BUILDING. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Nariman Point / Fort1 km
Lower Parel / Worli business district9 km
Bandra Kurla Complex (BKC)18 km
Chhatrapati Shivaji Int'l Airport20 km
Powai / Hiranandani business park24 km
Andheri MIDC / SEEPZ25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara West

Kunal Height
declared completion Dec 2026 · Shree SAI Builders & Developers
Vimal Classic
declared completion Dec 2026 · OM Vimal Developers
Anant Tower E AND F
declared completion Dec 2026 · Shantinath Enterprises
Dhananjay Avenue
declared completion Dec 2026 · SAI Kiran Builder AND Developers
Sai Baba Nagar Residential With Shopline Building With A B C Wings
Not filing quarterly progress reports · declared completion Dec 2026 · Shreeji Associates
Baba SAI Palce CO-OP-HSG LTD
declared completion Dec 2026 · G R AND Sons
More projects in Palghar

Other RERA-registered projects in Palghar

Ideal Avenue
declared completion Dec 2027 · Yaduvanshi Enterprises
Ideal Avenue Building NO 3 Type B1D Wing B
declared completion Apr 2027 · Shree SAI Samarth Builders AND Developer
Ideal City Building NO3 Basant Kunj
declared completion Jun 2024 · Devbhoomi Builders AND Developers
Ideal Complex
declared completion Jun 2024 · Gajanan Builders & Developers
Ideal Garden
declared completion Mar 2028 · Gajanan Builders & Developers
Ideal Garden
declared completion Dec 2025 · Shree Shiv Kripa Builders & Develope

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.