Mumbai/Project record

MahaRERA · the public record

JANHAVI

Mumbai Suburban · SHILPA PARAG THAKKAR

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for JANHAVI

MahaRERA · P52000008660

Delivery and registration

When is the project declared for completion?

JANHAVI is registered with MahaRERA as P52000008660 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

46months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000008660
Registered on19 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JANHAVI record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SHILPA PARAG THAKKAR is the promoter of record on 7 projects registered with MahaRERA.

7projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JANHAVI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
JANHAVI1G+4-

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for JANHAVI, with orders passed in 7 of them.

7complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002369218/03/2018Mathew Thomas vs Shree Mahalaxmi Builders & Developersorder passed
CC00600000004443611/07/2018DR. PRIYA I. ROHRA vs SHILPA PARAG THAKKARorder passed
CC00600000007844812/03/2019RAKESH SHARAD DESAI vs SHREE MAHALAXMI BUILDERSorder passed
CC00600000021033320/03/2022Pundalik Tukaram Lad vs Shree Mahalaxmi Builders & Developersorder passed
CC00600000021046720/03/2022ARVIND ANGU JATHAN vs Shilpa Parag Thakkarorder passed
CC00600000021047220/03/2022shakil shaikh vs Shilpa Parag Thakkarorder passed
CC00600000039642425/06/2023DEVYANI ABHAY PAWAR vs SHILPA PARAG THAKKARorder passed

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 410101. Per the filed land record, the plot is bounded to the north by SURVEY NO 65, to the south by SURVEY NO 85 PLOT NO 34, to the east by SURVEY NO 65 and to the west by SURVEY NO 85 PLOT NO 25. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 48 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park48 km
Bandra Kurla Complex (BKC)51 km
Chhatrapati Shivaji Int'l Airport51 km
Andheri MIDC / SEEPZ52 km
Lower Parel / Worli business district55 km
Nariman Point / Fort57 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

Labdhi Gardens Phase 6
declared completion Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
declared completion Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
declared completion Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
declared completion Dec 2026 · Nehaldhara Realtors
SG Skytown
Not filing quarterly progress reports · declared completion Dec 2026 · S G Group
THE Green Orchid Phase III
declared completion Dec 2026 · Shakti Developers
More builders in Neral

Major developers building in Neral

More projects in Raigarh

Other RERA-registered projects in Raigarh

Janki
declared completion Dec 2024 · Neelkanth Associates
Janki Niwas
declared completion Jun 2027 · Dwinetra Developers
Janki Villa
declared completion Mar 2025 · Shree Krishna Builders
Jasmine
declared completion Dec 2031 · Persipina Developers Private Limited
JAY Ganesh Residency
declared completion Dec 2022 · JAY Ganesh Developers
JAY Vijay Ngar - Bldg. NO. 2 - A AND B Wing
declared completion Mar 2022 · Sunderlal Aklinglal Jain

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.