Mumbai/Project record

MahaRERA · the public record

KRISHNA PALACE

BORIVALI WEST · PANTAGON BUILT

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for KRISHNA PALACE

MahaRERA · P51800002538

Delivery and registration

When is the project declared for completion?

KRISHNA PALACE is registered with MahaRERA as P51800002538 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800002538
Registered on01 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KRISHNA PALACE record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KRISHNA PALACE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
KRISHNA PALACE1G+2330 Dec 2023

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for KRISHNA PALACE, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004447611/05/2018JAGRUTI LAD vs Pantagon Builtorder passed
CC00600000019601115/02/2021Manjula Nandagopal vs Lucina Land Development Limitedorder passed
CC00600000019613623/02/2021MR. KRISHNARAJ M. POONJA AND MRS. RESHMA K. POONJA vs M/S PENTAGON BUILTorder passed
CC00600000019621902/03/2021MR. KRISHNARAJ MANJANNA POONJA AND MRS. RESHMA KRISHNARAJ POONJA vs M/S PENTAGON BUILT, MR. MUKESH RATILAL MAKWANA, MR. BHAVESH NAVNITLAL SHAHorder passed
CC00600000019743128/06/2021PANTAGON BUILT vs KRISHNARAJ MANJANNA POONJAorder passed
CC00600000019599812/02/2021Colin Desa vs M/s Pantagon Builtorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023The primary reasons of delay was obtaining approvals on time for the Rehab building and Sale Building. Enormous numbers of compliance, lengthy procedures for required permissions,
30 Dec 202330 Dec 2025Further Permissions as well as Rehab Tenant flat handover balance and Occupation Certificate Balance.

Location, Land & Connectivity

Located at BORIVALI WEST, EKSAR ROAD, Borivali, Mumbai Suburban, 400091. Per the filed land record, the plot is bounded to the north by CTS - 314 PART, to the south by NALLA, to the east by EKSAR ROAD and to the west by NALLA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 12 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Bhoomi Pratishtha
declared completion Oct 2026 · Bhoomi Shashwat Estate Pvt. Ltd.
Bank OF India Employees Sukhada Chsl
declared completion Dec 2026 · M/S Hirani Realtors
Jaykant Bliss
declared completion Dec 2026 · Chitalia Builders
Gagansagar
declared completion Dec 2026 · HUM Developers Private Limited
Empire Meghna
declared completion Mar 2027 · Empire Realty
Goyal Nrupa Square
declared completion Mar 2027 · Parshwa Amrit
More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Krishna Residency
declared completion Dec 2027 · Rangoli Developers
Krishnagiri Upavan CO-Operative Housing Society Limited
declared completion Dec 2029 · Samarpan Homes & Developers
Krishnaraj Buildcon NEW Suryadarshan CO OP Hsg. SOC
declared completion Dec 2027 · Krishnaraj Buildcon
Krishvi Residency
declared completion Dec 2027 · Shagun Chembur
Krystel By Kams Realtors
declared completion Dec 2026 · Kams Realtors
Kshitij Eminence
declared completion Jun 2026 · Kshitij Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.