Le Jardin

Raigarh · Gold Field Developers

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Mar 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Le Jardin

MahaRERA · P52000006764

Delivery and registration

When is the project declared for completion?

Le Jardin is registered with MahaRERA as P52000006764 and the promoter has declared completion for 30 Mar 2023.

30 Mar 2023

declared completion

43months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000006764
Registered on16 Aug 2017
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Le Jardin record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Le Jardin in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Le Jardin1G+331 Dec 2018

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Le Jardin, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000008962017/06/2019Nilesh Singit vs Jay Construction India, Mr. Jayesh Mistry and Mr. Manish Mistryorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 20191. The severe slow down in Housing Construction Sector due to which we could not achieve sale/booking target of flats/shops in spite of our best efforts. This slow down affected us
31 Dec 201930 Sep 20211. The severe slowdown in Housing Construction Sector due to which we could not achieve sale/booking target of flats/shops in spite of our extensive efforts. This slow down affecte
30 Sep 202130 Mar 2023The reasons for delay in completion are as under: 1. The severe slowdown in Housing Construction Sector, and more particularly from the time of outbreak of the Covid-19 pandemic,

Location, Land & Connectivity

Located at Karjat, Raigarh, 410201. Per the filed land record, the plot is bounded to the north by existing private road, to the south by next phase of promoter, to the east by Road Front and to the west by Rear Side towards proposed club building. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 48 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park48 km
Bandra Kurla Complex (BKC)50 km
Chhatrapati Shivaji Int'l Airport51 km
Andheri MIDC / SEEPZ52 km
Lower Parel / Worli business district52 km
Nariman Point / Fort53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Warai Woods Ph 2
Not filing quarterly progress reports · declared completion Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
declared completion Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
declared completion Dec 2026 · Balsam Builders
Beverly Hills
declared completion Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · declared completion Dec 2026 · Jupiter Heights
Adwait
Not filing quarterly progress reports · declared completion Dec 2026 · Venkatesh Developers
More builders in Karjat

Major developers building in Karjat

More projects in Raigarh

Other RERA-registered projects in Raigarh

Leelabai Residency
declared completion Aug 2023 · Prabhakar Gajanan Owalekar
Legacy Apartments
declared completion Apr 2023 · Suncity Builders AND Developers
Legacy Vrindavan
declared completion Dec 2027 · Concord Enterprises
Lifespace Delight
declared completion Jul 2022 · Lifespace Properties
Link Infra Properties
declared completion Jan 2021 · Link Infra Properties
LK Avanti
declared completion Dec 2026 · L K Infrastructure Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.