Mumbai/Project record

MahaRERA · the public record

METRO HIGHLAND - PHASE II

CHIKHALOLI · METRO DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2026declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for METRO HIGHLAND - PHASE II

MahaRERA · P51700024041

Delivery and registration

When is the project declared for completion?

METRO HIGHLAND - PHASE II is registered with MahaRERA as P51700024041 and the promoter has declared completion for 30 Jun 2026.

30 Jun 2026

declared completion

4months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700024041
Registered on16 Jan 2020
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for METRO HIGHLAND - PHASE II record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

METRO DEVELOPERS is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for METRO HIGHLAND - PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
R11G+830 Jun 2025
R21G+830 Jun 2025
R31G+830 Jun 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Filed descriptions (status fields empty): 4 “MATTER IS SUBJUDICE”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The Court Of Civil Judge S D Kalyan144/20132013Status not supplied
Filed description: MATTER IS SUBJUDICE
The Court Of Civil Judge S D Kalyan244/20132013Status not supplied
Filed description: MATTER IS SUBJUDICE
The Court Of Civil Judge S D Kalyan44/20182018Status not supplied
Filed description: MATTER IS SUBJUDICE
The Court Of Joint Civil Judge S D Kalyan265/20182018Status not supplied
Filed description: MATTER IS SUBJUDICE

Location, Land & Connectivity

Located at CHIKHALOLI, CHIKHALOLI ROAD, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by S NO 131, to the south by 18 MTR WIDE ROAD, to the east by S NO 128 H NO 1 PT and to the west by 12 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Meera Nanda Bliss
declared completion Nov 2026 · Meera Homes LLP
Raj Residency
declared completion Nov 2026 · Vijay Chahu Patil
Precious Empire Wing A, B AND C
declared completion Dec 2026 · RKR Reality
Chaitraban CHS
declared completion Dec 2026 · Annapurna Enterprises
Dipti Skycity Bldg No. 7
declared completion Dec 2026 · Dipti Home Makers Pvt Ltd
Imperial Heights
declared completion Dec 2026 · Krishna Developers
More builders in Ambernath

Major developers building in Ambernath

More projects in Thane

Other RERA-registered projects in Thane

Metro Hive D-1
declared completion Dec 2026 · Vihang Infrastructure PVT LTD
Metro Imperial
declared completion Dec 2028 · Pragati Combines
Metro Luxuria
declared completion Dec 2027 · Nivara Engineers
Metro Majestic
declared completion Nov 2024 · Nakshatra Builders
Metro Regalia
declared completion Dec 2027 · Shree Ashtavinayak Enterprises
Metropolis - Aquaris Phase 2
declared completion Sep 2025 · Anant Square

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.