135units filed as unsoldInventory · 23 October 2026
29 Mar 2025declared completionMahaRERA registration · read 18 Jul 2026
215registered unitsMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for NARAYAN SHOPPING PARK

MahaRERA · P99000016863

Delivery and registration

When is the project declared for completion?

NARAYAN SHOPPING PARK is registered with MahaRERA as P99000016863 and the promoter has declared completion for 29 Mar 2025.

29 Mar 2025

declared completion

19months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000016863
Registered on20 Jun 2018
Promoter-declared completion29 Mar 2025
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Sales

How many are filed as sold or booked?

In NARAYAN SHOPPING PARK, 80 of 215 units filed with MahaRERA are recorded as sold or booked, about 37%, and 135 are filed as unsold.

37%sold or booked

80 of 215 units

₹15.64 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹15.64 Cr (about 100%) is recorded as collected and ₹0 as receivable.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 80 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹5,384/sqft, with eight in ten falling between ₹4,263 and ₹12,924 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, unit by unit

Read from MahaRERA on 23 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 80 units carry one, and 135 of the 215 are recorded unsold.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
Building No-1 D Wing-101369 sqftRs 19.85 lakh typical, over Rs 13.50 lakh to Rs 22.00 lakh17 filed · similar area (within 2%), elsewhere in project

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In NARAYAN SHOPPING PARK, 108 of the 135 unsold units have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 134 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 215 units are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
Building No-1 A Wing1G+42531 Dec 2022
Building No-1 B Wing1G+43631 Dec 2022
Building No-1 C Wing1G+31931 Dec 2022
Building No-1 D Wing1G+31931 Dec 2022
Building No-2 A WIng1G+42731 Dec 2022
Building No-2 B Wing1G+43631 Dec 2022
Building No-2 C Wing1G+31931 Dec 2022
Building No-31G+43431 Dec 2022

Unit mix on the filing: 148 residential and 67 non-residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2024Due to covid unavailablity of material and labour
29 Dec 202429 Mar 2025OC was received 3 months after rera completion date & hence not uploaded. Taking extension to upload the OC

Location, Land & Connectivity

Located at NEAR GANESH KUND, BOISAR(EAST) , Dist.-PALGHAR, S NO. 22/3/23/3, Yadav Nagar Naka, Palghar, Palghar, 401501. Per the filed land record, the plot is bounded to the north by S N 66 AND 67, to the south by S NO 65 PART 1 AND 2, to the east by S N 65 PART 2 S N 137 and to the west by S N 65 PART 1 SN 64. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 76 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ76 km
Powai / Hiranandani business park78 km
Chhatrapati Shivaji Int'l Airport81 km
Bandra Kurla Complex (BKC)83 km
Lower Parel / Worli business district90 km
Nariman Point / Fort98 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Marathe Complex
declared completion Dec 2026 · Gprs Realty
Rajhans United Regency III
declared completion Dec 2026 · Rajhans Homes
Yash Padma
declared completion Dec 2026 · SAI Shraddha Enterprises
Avani Residency
declared completion Dec 2026 · Avani Residency
Avasar Residency
declared completion Dec 2026 · Amico Builder
Bhakti Apartment Phase II
declared completion Dec 2026 · Saryu Builders & Developers
More projects in Palghar

Other RERA-registered projects in Palghar

Narayani Arcade
declared completion Mar 2026 · Narayani Estate
Narayani Darshan
declared completion Dec 2019 · Narayani Enterprises
Narayani Darshan Building NO. 5, Type - D
declared completion Dec 2028 · Shivalik Realtors
Narayani Darshan Building No-7
declared completion Oct 2025 · Narayani Enterprises
Narayani Residency`
declared completion May 2030 · Himanshu Sham Tendulkar
Narendra Heights
declared completion Dec 2030 · Brijesh Narendra Singh

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.