Mumbai/Project record

MahaRERA · the public record

NEELAM PEARL

CHINCHAVALI SHEKIN KHOPOLI · ARVIND UMERSHI SHAH

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for NEELAM PEARL

MahaRERA · P52000024595

Delivery and registration

When is the project declared for completion?

NEELAM PEARL is registered with MahaRERA as P52000024595 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

46months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000024595
Registered on24 Feb 2020
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEELAM PEARL record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Deregistered — MahaRERA has deregistered this project — it is off the register.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NEELAM PEARL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
NEELAM PEARL1G+631 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at CHINCHAVALI SHEKIN KHOPOLI, PLOT NO 1 CTS NO 1601, Andheri, Mumbai Suburban, 410202. Per the filed land record, the plot is bounded to the north by CTS NO 1136, to the south by CTS NO 1600, to the east by CTS NO 1315 and to the west by 18 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khalapur

Indiabulls Savroli - 3
declared completion Dec 2026 · Sylvanus Properties Limited
K P Tower – Vimal Heights
declared completion Dec 2027 · Kishor Kapoorchand Porwal
Magic Hill Enclave
declared completion Dec 2027 · Garnet Construction Ltd.
Shree Swami Samarth
declared completion Dec 2027 · Jayawant Janardan Bahadkar
Vrindavan Flora - Phase III - Bldg NO - 4
declared completion Dec 2027 · Thalia Vastu Infra Projects
Krushna Riverside
declared completion Feb 2028 · Shree Krushna Enterprises
More builders in Khalapur

Major developers building in Khalapur

More projects in Raigarh

Other RERA-registered projects in Raigarh

Neelkanth Aangan
declared completion Dec 2022 · Ravriya Developers
Neelkanth Auris
declared completion May 2027 · Neelkanth Infracon
Neelkanth Avenue
declared completion Jun 2026 · Skytech Infra
Neelkanth Bliss
declared completion Dec 2023 · Maharashtra Developers
Neelkanth Complex
declared completion Dec 2027 · Neelkanth Mahadev Developers
Neelkanth Darshan
declared completion Dec 2024 · Skytech Infra

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.