Parmarth Niketan - Redevelopment of Mani Bhuvan

Daulat Nagar · J V Constructions & Developers

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Parmarth Niketan - Redevelopment of Mani Bhuvan

MahaRERA · P51800001745

Delivery and registration

When is the project declared for completion?

Parmarth Niketan - Redevelopment of Mani Bhuvan is registered with MahaRERA as P51800001745 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

40months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800001745
Registered on29 Jul 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Parmarth Niketan - Redevelopment of Mani Bhuvan in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Parmarth Niketan - Redevelopment of Mani Bhuvan1G+1430 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 12 court cases on this project to MahaRERA. Filed descriptions (status fields empty): 3 “Hearing on Notice of Motion”; 9 “Evidence”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court Goregaon Dindoshi3432015Status not supplied
Filed description: Hearing on Notice of Motion
City Civil Court Goregaon Dindoshi3442015Status not supplied
Filed description: Hearing on Notice of Motion
City Civil Court Goregaon Dindoshi3452015Status not supplied
Filed description: Hearing on Notice of Motion
Small Cause Bandra1522010Status not supplied
Filed description: Evidence
Small Cause Bandra1532010Status not supplied
Filed description: Evidence
Small Cause Bandra1542010Status not supplied
Filed description: Evidence
Small Cause Bandra832010Status not supplied
Filed description: Evidence
Small Cause Bandra842010Status not supplied
Filed description: Evidence
Small Cause Bandra852010Status not supplied
Filed description: Evidence
Small Cause Bandra5392013Status not supplied
Filed description: Evidence
Small Cause Bandra5402013Status not supplied
Filed description: Evidence
Small Cause Bandra5412013Status not supplied
Filed description: Evidence

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Commencement Certificate recently received on 05/03/2019 and therefore it is not possible for us to complete the project on or before 31/12/2019. 100 % consent of the allottees is
30 Apr 202030 Apr 2020C.C is not granted by MCGM due to non compliance of some of the IOD conditions and that there are 3 Tenants who have field suit in the court in the year 2015. We have given underta
30 Apr 202031 Dec 2022Initially the proposed date of completion of the project was 31/12/2019. Subsequently an extension for 1 year under Section 6 of RERA was applied to which the RERA Authority grante

Location, Land & Connectivity

Located at Daulat Nagar, Road no. 7, Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by By CTS No 2690 and 2691, to the south by By CTS No 2686, to the east by Daulat Nagar Road No 7 and to the west by By CTS No 2689. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 12 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park14 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Chandratej CHS LTD
declared completion Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
declared completion Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
declared completion Oct 2026 · Balaji Enterprises
Empire Vrindavan
declared completion Nov 2026 · Empire Realty
66 Avenue
declared completion Dec 2026 · Parsh Realtors
Anand CO-Operative Housing Society LTD Building NO 2
declared completion Dec 2026 · Samarpan Homes & Developers
More builders in Borivali East

Major developers building in Borivali East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Parmatma Villa
declared completion Dec 2028 · Shrikant Satyanarayan Agarwal
Parque Residences
declared completion Dec 2028 · M/s. New Grid Buildcon LLP
Parshuram Heights
declared completion Sep 2028 · Spacewalk Realty LLP
Parshva Avenue
declared completion Dec 2027 · Aarsh Construction
Parshwa Darshan CO Operative Housing Society Limited
declared completion Dec 2027 · Svecha Realty LLP
Parshwa Darshan Phase 1
declared completion Dec 2027 · Aarsh Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.