Pushpak Node Dapoli · Raigarh

PRIME JADE

MahaRERA P52000049977 · promoter Prime Landmarks

What registered buyers actually paid

₹8,103 – ₹10,349

per sq ft of carpet, agreement value

Covers 80% of 27 agreements filed with MahaRERA.i

Free example from the dataActual RERA data

Home

B-102

Carpet area

321 sq ft

Typical value

₹31.3 lakh

Homes of the same size₹25.9–34 lakh16 registered
See prices for 59 more homesEvery unit and floor, from the filings.Get the Sales Report, ₹2,999 →
On payment30-day refundMahaRERA source
Which home should I ask for?Get the Drawings Report₹4,999 · floor plans, approved drawings and what sits around each home.

Independent analysis · Quietlist · Bengaluru
Paid through Razorpay · WhatsApp +91 86608 81791

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

PRIME JADE is registered with MahaRERA as P52000049977 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000049977
Registered on06 Mar 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRIME JADE record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

Construction

How much construction cost has been reported?

In PRIME JADE, ₹82.93 Lakh of a declared ₹9.20 Cr estimated project cost is reported as incurred, about 9.0%, as at the last certified filing with MahaRERA.

9.0%

₹82.93 Lakh

of ₹9.20 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In PRIME JADE, 27 of 87 homes filed with MahaRERA are recorded as sold or booked, about 31%, and 60 remain available.

31%sold

27 of 87 homes

₹8.46 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹5.29 Cr (about 63%) is recorded as collected and ₹3.16 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 27 registered agreements, the effective carpet rate is ₹9,703/sqft, with eight in ten falling between ₹8,103 and ₹10,349 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 07 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 27 homes carry one, and 60 of the 87 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B-102321 sqftRs 31.27 lakh typical, over Rs 25.93 lakh to Rs 33.96 lakh16 filed at this size

A filed consideration is what was registered for one {unit}. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the {unit} is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In PRIME JADE, 43 of the 60 unsold homes have agreements filed on their own stack. The Sales Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 59 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 87 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
PRIME JADE A WING1G+45331 Dec 2025
PRIME JADE B WING1G+43431 Dec 2025

Unit mix on the filing: 80 residential and 7 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2027The project execution was delayed due to late receipt of the Commencement Certificate (CC) from the competent authority, resulting in delay in construction activities and pending b

Location, Land & Connectivity

Located at Pushpak Node Dapoli, Sector 3 Dapoli, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by 11 M WIDE ROAD, to the south by PLOT NO 423, to the east by PLOT NO 452 and to the west by PLOT NO 450. These are the boundaries as recorded in the filed land record.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which home to ask for · Drawings Report

The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

2approved drawings on file
7other papers filed

Everything above is on this page already, free, from the government record. The drawings are different: the 2 approved sheets are the same drawings the builder filed to get PRIME JADE approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Prime Landmarks is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Panvel

Arihant Clan Aalishan Phase I
possession by Sep 2026 · Arihant Vatika Realty Private Limited
Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Delta Hills
possession by Sep 2026 · Shree Ganesh Enterprises
Delta Riviera
possession by Sep 2026 · Shreenathji Organisers Pvt. Ltd.
GAJ Oasis
possession by Sep 2026 · Shiv Builders AND Developers
Green View
possession by Sep 2026 · Siddhivinayak Developers

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Prime Neelkanth
possession by Dec 2028 · Prime Neelkanth LLP
Prime Opal
declared completion Jun 2026 · Prime Abhishek Buildcon
Prime Pearl
declared completion Dec 2024 · Prime Abhishek Buildcon
Prime Rose
possession by Mar 2027 · AK Hitech Associates
Prime Ruby
declared completion Dec 2024 · Prime Abhishek Buildcon
Prime Solitaire
declared completion Oct 2025 · Prime Builders AND Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 10 Sep 2026