Mumbai/Project record

MahaRERA · the public record

RADIANCE REGALIA

KANHERI · RADIANCE BUILDERS AND DEVELOPERS LLP

Is this the right project?
Which unit should you choose?

Read the free RERA facts below. For help choosing a unit or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Apr 2029declared completionMahaRERA registration · read 11 Sep 2026
11registered unitsMahaRERA registration · read 11 Sep 2026
Certificate Signedregistration statusMahaRERA registration · read 11 Sep 2026

Free project details

Registration read 11 Sep 2026

RERA details for RADIANCE REGALIA

MahaRERA · PM1180002601210

Delivery and registration

When is the project declared for completion?

RADIANCE REGALIA is registered with MahaRERA as PM1180002601210 and the promoter has declared completion for 30 Apr 2029.

30 Apr 2029

declared completion

30months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 11 Sep 2026

MahaRERA registrationPM1180002601210
Registered on16 Jul 2026
Promoter-declared completion30 Apr 2029
Current statusCertificate Signed
Against today30 months to the declared date

Sales

How many are filed as sold or booked?

In RADIANCE REGALIA, 0 of 4 units filed with MahaRERA are recorded as sold or booked, about 0%, and 4 are filed as unsold.

0%sold or booked

0 of 4 units

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The registration lists 11 units; this inventory lists 4. These are separate filed records. Their counts do not match; neither count establishes today's availability.

Source · MahaRERA sold/unsold inventory filing · read 11 Sep 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the unit.

FloorUnitCarpetGovt reckoner value
Floor 1102581 sqft (53.96 sqm)₹77.55 Lakh
Floor 2202581 sqft (53.96 sqm)₹77.55 Lakh
Floor 3304414 sqft (38.46 sqm)₹55.28 Lakh
Ground/Floor 01468 sqft (43.48 sqm)₹71.87 Lakh

The inventory filing also declares: 3 reserved.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RADIANCE REGALIA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 11 Sep 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3 and 11 units are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
RADIANCE REGALIA1G+311-

Unit mix on the filing: 10 residential and 1 non-residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2029NA

Location, Land & Connectivity

Located at KANHERI, Dattapada Road, Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by 9.10M WIDE DP ROAD, to the south by CTS 95 & 96 OF MAGATHANE VILLAGE, to the east by CTS 261 OF KANHERI VILLAGE and to the west by CTS 259 OF KANHERI VILLAGE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 10 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ10 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district25 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Chandratej CHS LTD
declared completion Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
declared completion Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
declared completion Oct 2026 · Balaji Enterprises
Empire Vrindavan
declared completion Nov 2026 · Empire Realty
66 Avenue
declared completion Dec 2026 · Parsh Realtors
Anand CO-Operative Housing Society LTD Building NO 2
declared completion Dec 2026 · Samarpan Homes & Developers
More builders in Borivali East

Major developers building in Borivali East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Radiant 59
declared completion Dec 2026 · Veer Jalaram Developers
Radius Residency And Anand Bhuvan
declared completion Dec 2023 · Radius Project Developers LLP
Rafiq Residency
declared completion Jun 2025 · Al Ammar Developers
Raghav Ananta
declared completion Dec 2027 · Raghav RAJ Builders & Developers LLP
Raghav Avenue
declared completion Jun 2029 · Raghav RAJ Builders & Developers LLP
Raghav Enclave
declared completion Dec 2027 · Raghav RAJ Builders & Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 19 Jul 2026. Document and inventory dates are shown in their sections.