Mumbai/Project record

MahaRERA · the public record

REGENCY PLAZA

NERAL EAST · VIRENDRA ANNNA JADHAV

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for REGENCY PLAZA

MahaRERA · P52000023919

Delivery and registration

When is the project declared for completion?

REGENCY PLAZA is registered with MahaRERA as P52000023919 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000023919
Registered on14 Jan 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for REGENCY PLAZA record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for REGENCY PLAZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
WING G1G+431 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NERAL EAST, SURVEY nO. 372, PLOT NO. 1,2,3,4, Karjat, Raigarh, 410101. Per the filed land record, the plot is bounded to the north by 18 METER DP ROAD, to the south by 9 METER INTERNAL ROAD, to the east by OPEN SPACE and to the west by 6 METER INTERNAL ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

Labdhi Gardens Phase 6
declared completion Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
declared completion Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
declared completion Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
declared completion Dec 2026 · Nehaldhara Realtors
SG Skytown
Not filing quarterly progress reports · declared completion Dec 2026 · S G Group
THE Green Orchid Phase III
declared completion Dec 2026 · Shakti Developers
More builders in Neral

Major developers building in Neral

More projects in Raigarh

Other RERA-registered projects in Raigarh

Regents Park Kharghar
declared completion Jun 2027 · Metro Satyam Developers
Regius Luxe
declared completion Dec 2027 · Bhagwanji Dharamshi Minat
Relish Galaxy
declared completion Dec 2026 · Mukesh Jayantilal Chouhan
Renaissance Royal Phase 1
declared completion Dec 2026 · Shree Sharada Infrastructures
Renaissance Royal Phase II
declared completion Dec 2028 · Shree Sharada Infrastructures
Renucorp Vanaha
declared completion Mar 2029 · Renucorp Rrudra Infra LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.