Mumbai/Project record

MahaRERA · the public record

SADGURU LANDMARK - WING A and E

TITWALA · SADGURU GROUP

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SADGURU LANDMARK - WING A and E

MahaRERA · P51700016355

Delivery and registration

When is the project declared for completion?

SADGURU LANDMARK - WING A and E is registered with MahaRERA as P51700016355 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700016355
Registered on08 May 2018
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SADGURU LANDMARK - WING A and E record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SADGURU LANDMARK - WING A and E in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
WING - A1G+731 Dec 2021
WING - E1G+731 Dec 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SADGURU LANDMARK - WING A and E, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC1250106229/03/2025M/s Sadguru Landmark Building No. 1 vs Mr Vijaykumar somlal Patel partner of Sadguru grouppending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023The main reason for of delay is that in the F.Y.2020-21, due to spread of COVID-19 in India, nationwide lockdown and migration of labour there was extreme shortage of material and

Location, Land & Connectivity

Located at TITWALA, TITWALA, Ambarnath, Thane, 421605. Per the filed land record, the plot is bounded to the north by S NO 104 H NO 5 AND S NO 107, to the south by S NO 104 H NO 7 AND 14, to the east by ADJOINING 24 MTR DP ROAD and to the west by ADJOINING OPEN LAND. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 39 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park39 km
Andheri MIDC / SEEPZ42 km
Chhatrapati Shivaji Int'l Airport44 km
Bandra Kurla Complex (BKC)45 km
Lower Parel / Worli business district53 km
Nariman Point / Fort59 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Titwala

Indrayani
declared completion Oct 2026 · Naresh Yashwant Patil
Mantra
declared completion Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
declared completion Nov 2026 · Rustagi Estates Private Limited
Ganpati Prasanna
declared completion Dec 2026 · Vijay Prabhakar Patil
Hillcrest Appartments
Registration suspended · declared completion Dec 2026 · Aasanghar Construction
Kalas Darshan
declared completion Dec 2026 · JAY Ganesh Developers
More projects in Thane

Other RERA-registered projects in Thane

Sadguru Nakshtra Phase III
declared completion Dec 2027 · Sadguru Developers
Sadguru Park-Phase I
declared completion Dec 2018 · Jagdish Shiwanand Wagh
Sadguru Shree Swami Samarth Residency
declared completion May 2029 · Shreesadguru Infrabuild LLP
Sadguru Symphony, Wing - D Of Phase - II
declared completion Dec 2022 · Sadguru Infra
Sadhana Sadan
declared completion Sep 2027 · SM Life Space Private Limited
Sadri Plaza
declared completion Dec 2025 · Shubh Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.