SHANTI NIKETAN

Mumbai Suburban · MATRIX CONSTRUCTIONS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Oct 2020declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SHANTI NIKETAN

MahaRERA · P51800008789

Delivery and registration

When is the project declared for completion?

SHANTI NIKETAN is registered with MahaRERA as P51800008789 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800008789
Registered on19 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHANTI NIKETAN record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

MATRIX CONSTRUCTIONS is the promoter of record on 6 projects registered with MahaRERA.

6projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHANTI NIKETAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
SHANTI NIKETAN1G+19-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SHANTI NIKETAN, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001202420/11/2017Darshan Mohan Tawde vs PAWAN ASHOK THARWANIorder passed
CC00600000010035101/08/2019Manisha Hitendra Varale vs Matrix Constructionsorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Change of planning authority from MCGM to MHADA

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400083. Per the filed land record, the plot is bounded to the north by BLDG NO 15, to the south by BLDG NO 13, to the east by 12 20 MT WIDE ROAD and to the west by EASTERN EXP HIGHWAY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 1 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport2 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district10 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vikhroli East

Meadows 83
declared completion Oct 2026 · Shreeji Realtors
Eastern Groves Phase 2
declared completion Dec 2026 · VL Savli Developers LLP
GS Casa
declared completion Dec 2026 · Prach Realcon LLP
GS Pearl
declared completion Dec 2026 · Prach Realcon LLP
Gurukrupa Darshanam
declared completion Dec 2026 · Gurukrupa Group Builders AND Developers
Kannamwar Nagar Datta Niwas
declared completion Dec 2026 · Vighnaharta Heights Private Limited
More builders in Vikhroli East

Major developers building in Vikhroli East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Shanti Sadan
declared completion Dec 2017 · MAN Global Ltd.
Shanti Sadan
declared completion Dec 2026 · Shree Hans Realtors LLP
Shantiniketan
declared completion May 2025 · Namorealty AND Infra LLP
Shantiniketan 2 CHS LTD
declared completion Nov 2020 · S D Bhalerao Constructions PVT LTD
Sharanya
declared completion Dec 2026 · M/S Satsang Enterprises
Sharda Heights
declared completion Dec 2018 · Narendra Jagdishprasad Agarwal

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.