Mumbai/Project record

MahaRERA · the public record

USHAJOSHI PARK PHASE II

Thane · J K T GROUP

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for USHAJOSHI PARK PHASE II

MahaRERA · P51700007222

Delivery and registration

When is the project declared for completion?

USHAJOSHI PARK PHASE II is registered with MahaRERA as P51700007222 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

40months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700007222
Registered on17 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for USHAJOSHI PARK PHASE II record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

J K T GROUP is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for USHAJOSHI PARK PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
B21G+331 Dec 2020
F11G+331 Dec 2020
C11G+331 Dec 2020
BUILDING A, WING-B1G+331 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023we hereby apply extension of the project Name USHA JOSHI PARK PHASE II registered with the regulatory authority vide project registration certificate bearing No. P517000007222 whic

Location, Land & Connectivity

Located at Kalyan, Thane, 421605. Per the filed land record, the plot is bounded to the north by ROAD, to the south by GAOTHAN, to the east by USHA JOSHI PARK and to the west by USHA JOSHI PARK. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 41 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park41 km
Andheri MIDC / SEEPZ43 km
Chhatrapati Shivaji Int'l Airport47 km
Bandra Kurla Complex (BKC)48 km
Lower Parel / Worli business district56 km
Nariman Point / Fort63 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Titwala

Indrayani
declared completion Oct 2026 · Naresh Yashwant Patil
Mantra
declared completion Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
declared completion Nov 2026 · Rustagi Estates Private Limited
Ganpati Prasanna
declared completion Dec 2026 · Vijay Prabhakar Patil
Hillcrest Appartments
Registration suspended · declared completion Dec 2026 · Aasanghar Construction
Kalas Darshan
declared completion Dec 2026 · JAY Ganesh Developers
More projects in Thane

Other RERA-registered projects in Thane

Ushakiran Enclave
declared completion Dec 2028 · Jayant Enterprises
Utsav
declared completion Jan 2028 · Clublife Realtors Private Limited
V-10 Lake View
declared completion Dec 2027 · V TEN Realty Private Limited
V A Business Centre
declared completion Dec 2027 · Shradhha Saburi Associates
V Kanta
declared completion Dec 2032 · Tarang Developers
V. M. Heights
declared completion Dec 2022 · Swayam Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.