VANGANI DARSHAN PHASE 1

Karav Village · Panika Infrastructures Pvt. Ltd.

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for VANGANI DARSHAN PHASE 1

MahaRERA · P51700003380

Delivery and registration

When is the project declared for completion?

VANGANI DARSHAN PHASE 1 is registered with MahaRERA as P51700003380 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700003380
Registered on05 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VANGANI DARSHAN PHASE 1 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VANGANI DARSHAN PHASE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A11G+4-
A21G+4-
A31G+4-
C1G+4-
B1G+4-

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for VANGANI DARSHAN PHASE 1, with orders passed in 5 of them.

7complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005583117/08/2018PAWAN GHANSHYAM GOPLANI vs PANIKA INFRASTRUCTURE PVT. LTD.order passed
CC1240043016/10/2024Premkumar Lalsingh Pathare vs Panika Infrastructures Pvt. Ltd.order passed
CC1240047219/10/2024Doreen Loraine Moniz vs Panika Infrastructures Pvt. Ltd.order passed
CC1240055924/10/2024Gaurav Suryakant Lohar vs Panika Infrastructures Pvt. Ltd.order passed
CC1240055724/10/2024Baburao Dashrath Wankhede vs Panika Infrastructures Pvt. Ltd.order passed
CC1260141414/03/2026Vishwas Jainwal vs Panika Infrastructures Pvt. Ltd.pending / no order on file
CC1260141714/03/2026ANWAR ABDUL RAZAK SHAIKH vs Panika Infrastructures Pvt. Ltd.pending / no order on file

Location, Land & Connectivity

Located at Karav Village, Karav Rd., Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by ROAD, to the south by G NO 3, to the east by G NO 2 REMAINING and to the west by G NO 1 . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 43 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park43 km
Andheri MIDC / SEEPZ47 km
Bandra Kurla Complex (BKC)47 km
Chhatrapati Shivaji Int'l Airport47 km
Lower Parel / Worli business district53 km
Nariman Point / Fort56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Aarya Prem CO-OP HSG SOC
declared completion Oct 2026 · K S Builders & Developers
Vishnu Vatika NX Phase II D & H Wing
declared completion Oct 2026 · M/s. Vishnu Group
JAY Ramdarshan CHS LTD
declared completion Nov 2026 · Mitra Buildcon
SAI Darshan
declared completion Nov 2026 · SAI Krupa Builders
Vastu Rachana
declared completion Dec 2026 · Gagangiri Infra
Prabhu Darshan CO-Operative Housing Society Limited
declared completion Dec 2026 · NYP Developers
More builders in Badlapur

Major developers building in Badlapur

More projects in Thane

Other RERA-registered projects in Thane

Vanya Arcade
declared completion Jun 2027 · R A Infrastructure
Varad Ashish
declared completion May 2026 · Varad Realtors
Varad Vinayak Complex Building C
declared completion Dec 2027 · Shree Balaji Builders & Developers
Varada Heights
declared completion Oct 2022 · Surendra Motiram Mhatre
Vardhaman Enclave
declared completion Dec 2026 · Vardhaman Builders
Vardhaman Kutir
declared completion Dec 2023 · Vardhaman Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.