VARDHAMAN TOWER

ROHA · VARDHAMAN TOWER

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

24 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

24 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000033302

Delivery and registration

When is the project declared for completion?

VARDHAMAN TOWER is registered with MahaRERA as P52000033302 and the promoter has declared completion for 24 Dec 2026.

24 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000033302
Registered on15 Feb 2022
Promoter-declared completion24 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VARDHAMAN TOWER record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Vardhaman Tower is the promoter of record on 47 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

47projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VARDHAMAN TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A WING1G+724 Dec 2026
B WING1G+724 Dec 2026
C WING1G+724 Dec 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at ROHA, SURVEY NO 31/2 63A, Roha, Raigarh, 402109. Per the filed land record, the plot is bounded to the north by RAILWAY LINE, to the south by SURVEY NO 21 B, to the east by SURVEY NO 31 3 and to the west by SURVEY NO 63 B. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Roha

AK Platinum Tower
possession by Dec 2026 · Amit Shashikant Khatu
Ankit Fiona Phase 2
Not filing quarterly progress reports · possession by Dec 2026 · Mahesh Suhas Padalkar
Chandradarshan Empire Phase II
possession by Dec 2026 · M/S R J Infra Developers
Hecc-SAI City
possession by Dec 2026 · Liyakat Anwar Hafiz
Mithila Icon
possession by Mar 2027 · N R Builders AND Develoeprs
Snehprabha Residency
possession by Mar 2027 · Dhanlaxmi Developers

Other RERA-registered projects in Raigarh

Vardhaman Vatika
possession by Jun 2027 · Vardhaman Enterprises
Vardhan Residency
declared completion Dec 2025 · Samrajya Associates LLP
Varleshwar Society Complex
declared completion Dec 2021 · Nisarg Prorety Developers
Varni Dham
declared completion Jun 2024 · Bhaveshwar Adobe
Varniraj 23
possession by Dec 2027 · Varniraj Group
Varniraj Crest
possession by Dec 2028 · Varniraj Nexus

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 13 Sep 2026