Mumbai/Project record

MahaRERA · the public record

Vrindavan Phase - I

Thane · SUNNY BUILDERS AND DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Vrindavan Phase - I

MahaRERA · P52000012103

Delivery and registration

When is the project declared for completion?

Vrindavan Phase - I is registered with MahaRERA as P52000012103 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

82months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000012103
Registered on01 Sep 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 82 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Vrindavan Phase - I record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SUNNY BUILDERS AND DEVELOPERS is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Vrindavan Phase - I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
ORCHID HOMES1G+431 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Thane, Thane, 410201. Per the filed land record, the plot is bounded to the north by HISSA NO 2 B, to the south by HISSA NO 4 B-1, to the east by HISSA NO 1 and to the west by HISSA NO 4A-1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 49 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park49 km
Bandra Kurla Complex (BKC)50 km
Chhatrapati Shivaji Int'l Airport51 km
Nariman Point / Fort52 km
Lower Parel / Worli business district52 km
Andheri MIDC / SEEPZ53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Warai Woods Ph 2
Not filing quarterly progress reports · declared completion Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
declared completion Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
declared completion Dec 2026 · Balsam Builders
Beverly Hills
declared completion Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · declared completion Dec 2026 · Jupiter Heights
Adwait
Not filing quarterly progress reports · declared completion Dec 2026 · Venkatesh Developers
More builders in Karjat

Major developers building in Karjat

More projects in Raigarh

Other RERA-registered projects in Raigarh

Vrindavan Phase - II
declared completion Dec 2027 · Sunny Builders AND Developers
Vrindavan Riverside
declared completion Dec 2026 · Greenscape Builders AND Developers
Vrundavan
declared completion Dec 2026 · A R Constructions
Vrundavan
declared completion Dec 2027 · Siddhivinayak Developers
Vrundavan Bliss
declared completion Dec 2027 · Vrundavan Lifespaces
Vrundavan Heights
declared completion Dec 2025 · Bayama Constructions

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.