Hadapsar · Pune

54 Flores Drive Phase 1

MahaRERA PM1261012502015 · promoter Swaraj Landmarks Llp

What registered buyers actually paid

₹9,909 – ₹11,746

per sq ft of carpet, agreement value

Covers 80% of 17 agreements filed with MahaRERA.i

Free example from the dataActual RERA data

Home

B1001

Carpet area

1,190 sq ft

Typical value

₹1.37 cr

Homes of the same size₹1.24–1.43 cr7 registered
See prices for 191 more homesEvery unit and floor, from the filings.Get the Sales Report, ₹2,999 →
On payment30-day refundMahaRERA source
Which home should I ask for?Get the Drawings Report₹4,999 · floor plans, approved drawings and what sits around each home.

Independent analysis · Quietlist · Bengaluru
Paid through Razorpay · WhatsApp +91 86608 81791

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

54 Flores Drive Phase 1 is registered with MahaRERA as PM1261012502015 and the promoter has declared completion for 30 Jun 2029.

30 Jun 2029

declared completion

33months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPM1261012502015
Registered on07 Jan 2026
Promoter-declared completion30 Jun 2029
Current statusCertificate Signed
Against today33 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 54 Flores Drive Phase 1 record 1 quarterly progress report since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026

Construction

How much construction cost has been reported?

In 54 Flores Drive Phase 1, ₹13.42 Cr of a declared ₹122.15 Cr estimated project cost is reported as incurred, about 11.0%, as at the last certified filing with MahaRERA.

11.0%

₹13.42 Cr

of ₹122.15 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 02 Jul 2026

Sales

How much has actually been sold?

In 54 Flores Drive Phase 1, 4 of 209 homes filed with MahaRERA are recorded as sold or booked, about 2%, and 205 remain available.

2%sold

4 of 209 homes

₹4.83 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹51.47 Lakh (about 11%) is recorded as collected and ₹4.31 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 04 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 17 homes carry one, and 192 of the 209 are recorded unsold. Since we started watching this ledger, 13 homes have moved out of the unsold list, most recently on 04 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B10011,190 sqftRs 1.3724 cr typical, over Rs 1.2369 cr to Rs 1.4259 cr7 filed at this size

A filed consideration is what was registered for one {unit}. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the {unit} is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In 54 Flores Drive Phase 1, 137 of the 192 unsold homes have agreements filed on their own stack. The Sales Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 191 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28 and 209 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building A1G+28107-
Building B1G+28102-

Unit mix on the filing: 196 residential and 13 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Hadapsar, CTS NO- 4592/1 (P), Plot No-54 (P) + CTS NO- 4592/2, Plot No- 55, Pune City, Pune, 411028. Per the filed land record, the plot is bounded to the north by D P Road, to the south by Plot No 54&56, to the east by D P Road and to the west by Plot No 55ノA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT2 km
Kharadi / EON IT Park6 km
Pune Junction / city centre7 km
Pune Int'l Airport (Lohegaon)10 km
Baner–Balewadi belt18 km
Hinjewadi Rajiv Gandhi IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which home to ask for · Drawings Report

The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

Everything above is on this page already, free, from the government record. The approved drawings are different: the sheets the builder filed to get 54 Flores Drive Phase 1 approved show what sits under each tower, which floor holds machines, and what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Swaraj Landmarks LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Swaraj Landmarks LLP

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing B
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

54 Flores Drive Phase 2
possession by Jun 2031 · Swaraj Landmarks LLP
55 Shashwat Avenue
possession by Dec 2027 · Shashwat Landmark
56 Kings Avenue
possession by Dec 2028 · Vastushree Infra Reality
57 Avenue
possession by Dec 2032 · Aquaris Properties Private Limited
57 Elevate
possession by Dec 2026 · Essen Venkatesh LLP
6, Boulevard
possession by Dec 2030 · SMP Namrata Lotus Landmarks LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 10 Sep 2026