Project RERA record · Pune

Archana Kohinoor Glory-Phase II

by Kohinoor Glory · MahaRERA P52100006997 · Certificate Signed · declared completion Dec 2023

Past its declared completion date

Past its declared completion date. Pune · YEREWADA

Past its declared completion date

The developer's declared completion date has passed on the MahaRERA register. The project may have completed late or may still be under construction — the register flags the declared timeline, not actual handover.

Archana Kohinoor Glory-Phase II is on MahaRERA's list of projects past their declared completion date. The register flags the declared timeline — the project may have completed late, may still be under construction, or may have obtained a RERA extension. The most direct check is to contact the developer for the current status and any revised RERA-filed timeline.

On the regulator's record

  • 26 quarterly reporting periods on MahaRERA's compliance schedule — no QPR default flagged

Source: MahaRERA public project record.

Builder track record

Kohinoor Glory is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Kohinoor Glory

Other RERA-registered projects in Yerwada

7 Business Square
Naiknavare Buildcon PVT LTD
Aaiji Business Center
Not Available
Arya
Zaheer Vakil Estates Private Limited
Belmont Lunar
Prasad Balasaheb Shinde

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Request the report on Archana Kohinoor Glory-Phase II

We analyse Archana Kohinoor Glory-Phase II in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Free · Risk Snapshot + alerts

The regulatory risk spine for Archana Kohinoor Glory-Phase II, emailed as a clean scorecard — plus an alert if the RERA status changes:

  • 🔴  Past its declared completion date

Something went wrong — email hello@quietlist.in.

✓ On its way to your inbox — plus alerts if the status changes.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Jul 2026