Khed · Pune

Chakan Annex

MahaRERA P52100002851 · promoter Sangam Realty

What registered buyers actually paid

₹5,170 – ₹6,047

per sq ft of carpet, agreement value

Covers 80% of 91 agreements filed with MahaRERA.i

Free example from the dataActual RERA data

Home

A2-104

Carpet area

239 sq ft

Typical value

₹14 lakh

Same stack, floors 1–6₹11–14.8 lakh48 registered
See prices for 7 more homesEvery unit and floor, from the filings.Get the Sales Report, ₹2,999 →
On payment30-day refundMahaRERA source
Which home should I ask for?Get the Drawings Report₹4,999 · floor plans, approved drawings and what sits around each home.

Independent analysis · Quietlist · Bengaluru
Paid through Razorpay · WhatsApp +91 86608 81791

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

Chakan Annex is registered with MahaRERA as P52100002851 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100002851
Registered on04 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Chakan Annex record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

Promoter record

What else is this promoter on record for?

Sangam Realty is the promoter of record on 16 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Chakan Annex, ₹8.90 Cr of a declared ₹10.89 Cr estimated project cost is reported as incurred, about 81.7%, as at the last certified filing with MahaRERA.

81.7%

₹8.90 Cr

of ₹10.89 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Chakan Annex, 43 of 164 homes filed with MahaRERA are recorded as sold or booked, about 26%, and 121 remain available.

26%sold

43 of 164 homes

₹5.86 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹5.85 Cr (about 100%) is recorded as collected and ₹26,030 as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 43 registered agreements, the effective carpet rate is ₹4,882/sqft, with eight in ten falling between ₹4,503 and ₹5,228 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 04 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 91 homes carry one, and 8 of the 124 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
A2-104239 sqftRs 13.99 lakh typical, over Rs 10.99 lakh to Rs 14.76 lakh48 filed on this stack, floors 1–6

A filed consideration is what was registered for one {unit}. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the {unit} is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Chakan Annex, every one of the 8 unsold homes has agreements filed on its own stack. The Sales Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 7 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 164 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A11G+76630 Jun 2019
A21G+79830 Jun 2019

Unit mix on the filing: 164 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Chakan Annex, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000017782921/03/2023Sangam Realty vs Mrs. Shanti Raju Sarodepending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Khed Cjjd4372014Disposed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021Due to delay in getting permissions of plinth checking certificate from PMRDA, Pune, we here request you that, we require 1 year extension for completion of our Chakan Annex projec
30 Jun 202130 Jun 2021Attached list of Allottes have consented to extend Rera date of completion of the project from 30/06/2021 to 30/06/2023
30 Jun 202130 Jun 2023Lockdown and labour shortage

Location, Land & Connectivity

Located at Khed, Chakan-Shikrapur Road, Pune City, Pune, 410501. Per the filed land record, the plot is bounded to the north by Chakan-Shikrapur Road, to the south by Zilla Parishad Road, to the east by Gat No 256 and to the west by Gat No 254. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)20 km
Hinjewadi Rajiv Gandhi IT Park22 km
Baner–Balewadi belt23 km
Kharadi / EON IT Park24 km
Pune Junction / city centre25 km
Magarpatta / Hadapsar IT27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which home to ask for · Drawings Report

The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

2approved drawings on file
16other papers filed

Everything above is on this page already, free, from the government record. The drawings are different: the 2 approved sheets are the same drawings the builder filed to get Chakan Annex approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sangam Realty is the promoter on 5 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Sangam Realty project & its RERA track record →

Other flagged projects by Sangam Realty

Sangam Realty
Past its declared completion datePune
Sangam Realty
Deregistered by MahaRERAPune
Sangam Realty
Deregistered by MahaRERAPune

Other RERA-registered projects in Chakan

Vallabh Heights
possession by Sep 2026 · G R Developers
Shree Samarth Shrushti
possession by Sep 2026 · Jagdamba Developers
Swapnapurti Heights
Not filing quarterly progress reports · possession by Oct 2026 · B R Developers
Richmond
possession by Oct 2026 · Coral Shubh Builders
Mungase Towers
possession by Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

Major developers building in Chakan

Other RERA-registered projects in Pune

Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP
Chakan Properties Phase II
declared completion Sep 2023 · Chakan Properties
Chakreshwar Vihar
possession by Dec 2028 · Yashodeep Tradecon
Chandan Apartment
declared completion Jun 2026 · Shree RAM Builders & Promoters
Chandan Colozium
declared completion Dec 2024 · Chandan Realities
Chandan Heights
declared completion Dec 2025 · OM Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 10 Sep 2026