PLAYTOR CHAKAN MIDC-PHASE 1

Savardari · Kumar Properties Lifespaces Private Limited

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

200units filed as unsoldInventory · 22 October 2026
30 Jun 2027declared completionMahaRERA registration · read 18 Jul 2026
262registered unitsMahaRERA registration · read 18 Jul 2026

From another project · Life Republic Atmos Phase II

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Life Republic Atmos Phase II Project Review · first page
First page of the complete sample.

Free project details

Registration read 18 Jul 2026

RERA details for PLAYTOR CHAKAN MIDC-PHASE 1

MahaRERA · P52100015448

Delivery and registration

When is the project declared for completion?

PLAYTOR CHAKAN MIDC-PHASE 1 is registered with MahaRERA as P52100015448 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100015448
Registered on27 Feb 2018
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today8 months to the declared date

Promoter record

What else is this promoter on record for?

Kumar Properties Lifespaces Private Limited is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

How many are filed as sold or booked?

In PLAYTOR CHAKAN MIDC-PHASE 1, 62 of 262 homes filed with MahaRERA are recorded as sold or booked, about 24%, and 200 are filed as unsold.

24%sold or booked

62 of 262 homes

₹9.79 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹8.03 Cr (about 82%) is recorded as collected and ₹1.76 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 62 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹5,393/sqft, with eight in ten falling between ₹4,910 and ₹5,582 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 22 October 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific home. On this project 62 homes carry one, and 200 of the 262 are recorded unsold.

Here is one home filed as unsold, beside the amounts filed for comparable homes:

HomeCarpetFiled comparisonBased on
C-1006248 sqftRs 5,390 a sq ft typical, over Rs 4,611 to Rs 7,49534 filed · nearby areas in the project (within 8%)

A filed consideration is the amount the promoter reported for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In PLAYTOR CHAKAN MIDC-PHASE 1, 80 of the 200 unsold homes have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 199 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14 and 262 homes are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
B1G+14131-
C1G+12131-

Unit mix on the filing: 262 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for PLAYTOR CHAKAN MIDC-PHASE 1, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC1250464127/12/2025Harish Chouknis vs PLAYTOR RAJGURUNAGAR DEVELOPERS PRIVATE LIMITEDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023shortage of building material, because of that
30 Dec 202330 Jun 2026The delay in the completion of the real estate project has been primarily caused by a combination of procurement issues, site conditions, coordination challenges, and Insufficient
30 Jun 202630 Jun 2027The delay and subsequent stall in the project's completion primarily arose due to unforeseen operational and cash flow limitations faced by the erstwhile promoter i.e, Playtor Rajg

Location, Land & Connectivity

Located at Savardari, Chakan MIDC Road, Pune City, Pune, 410501. Per the filed land record, the plot is bounded to the north by Adjacent Gat No 6, to the south by Adjacent Gat No 230, to the east by Open space of Project and to the west by Adjacent A bldg. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 20 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park20 km
Baner–Balewadi belt23 km
Pune Int'l Airport (Lohegaon)26 km
Pune Junction / city centre29 km
Kharadi / EON IT Park30 km
Magarpatta / Hadapsar IT32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chakan

Swapnapurti Heights
Not filing quarterly progress reports · declared completion Oct 2026 · B R Developers
Richmond
declared completion Oct 2026 · Coral Shubh Builders
Mungase Towers
declared completion Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
declared completion Dec 2026 · Chakan Business HUB LLP
Construction Of 400 EWS On Land Bearing No 818 P Chakan Pune
Not filing quarterly progress reports · declared completion Dec 2026 · Pune Housing And Area Development Board
Ivory Tathastu
declared completion Dec 2026 · Ivory Lifespace LLP
More builders in Chakan

Major developers building in Chakan

More projects in Pune

Other RERA-registered projects in Pune

Playtor Paud C- Phase 2
declared completion Jun 2024 · Sangam Realty
Playtor Paud D- Phase 1
declared completion Jun 2023 · Sangam Realty
Playtor Paud D- Phase 2
declared completion Sep 2026 · Sangam Realty
Playtor Ranjangaon Midc Phase 4
declared completion Apr 2033 · Sujit Santosh Bhansali
Playtor Ranjangaon- Phase 2
declared completion Jun 2022 · Playtor Lifespaces Private Limited
Playtor Ranjangaon- Phase 3
declared completion Dec 2023 · Playtor Lifespaces Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.