Pune/Project record

MahaRERA · the public record

EMINENCE PROJECT 2

VIMAN NAGAR · NAIKNAVAREDEVELPERSPVTLTD

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

1units filed as unsoldInventory · 23 October 2026
29 Mar 2025declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 19 Jul 2026

RERA details for EMINENCE PROJECT 2

MahaRERA · P52100018108

Delivery and registration

When is the project declared for completion?

EMINENCE PROJECT 2 is registered with MahaRERA as P52100018108 and the promoter has declared completion for 29 Mar 2025.

29 Mar 2025

declared completion

19months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52100018108
Registered on10 Oct 2018
Promoter-declared completion29 Mar 2025
Current statusCertificate Signed
Against todayabout 19 months past the declared date

What the filings record, unit by unit

Read from MahaRERA on 23 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 19 units carry one, and 1 of the 20 are recorded unsold.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
1011,969 sqftRs 14,045 a sq ft typical, over Rs 12,108 to Rs 16,6896 filed · nearby areas in the project (within 8%)

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In EMINENCE PROJECT 2, every one of the 1 unsold units has filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See all 19 filed sold/booked entries — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
BLDG B1G+8-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for EMINENCE PROJECT 2, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 19 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000026970003/11/2023Naiknavare Group vs Mrs. Sohan Lata Jhaorder passed
CC00500000047137724/07/2024SOHANLATA RAJU JHA vs NAIKNAVARE DEVELOPERSorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Filed descriptions (status fields empty): 1 “PENDING”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division Pune5832013Status not supplied
Filed description: PENDING

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2022Dear Sir, We have registered our Project EMINENCE PROJECT 2 No. P52100018108 under RERA. The completion date for the project is 30 TH SEPTEMBER 2021. But considering the COVID-19
30 Sep 202229 Mar 2024Date : 29.03.2023 To The Chief Engineer, RERA OFFICE, MUMBAI. Subject : Application for the Extension of "Eminence Project-2" Referance : Project Registration No. - P521000
29 Mar 202429 Mar 2025To MahaRERA MUMBAI Subject: Application for Extension of Project Completion Date for "Eminence Project 2" - RERA Registration Number: P52100018108 Dear Sir/Madam, We

Location, Land & Connectivity

Located at VIMAN NAGAR, VIMAN NAGAR, Pune City, Pune, 411047. Per the filed land record, the plot is bounded to the north by BY DP ROAD, to the south by BY PART OF S NO 231-2, to the east by BY PART OF S NO 231-2 and to the west by BY VIP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)2 km
Kharadi / EON IT Park4 km
Pune Junction / city centre6 km
Magarpatta / Hadapsar IT6 km
Baner–Balewadi belt14 km
Hinjewadi Rajiv Gandhi IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lohgaon

Youthika
declared completion Oct 2026 · Krushnarang Group
Pankaj Aasmaan Phase V
declared completion Dec 2026 · Pankaj Developers
Aayush Wisteria
declared completion Dec 2026 · Pritam Kantilal Khandve
Divine Garden Phase 1
declared completion Dec 2026 · Shriram Associates
Divine Garden Phase II
declared completion Dec 2026 · Shriram Associates
Goodwill Metropolis East Phase 2
declared completion Dec 2026 · Krishna Buildcon
More builders in Lohgaon

Major developers building in Lohgaon

More projects in Pune

Other RERA-registered projects in Pune

Emirus G
declared completion Jun 2022 · G M Kenjale Developers
Emisphere
declared completion Dec 2027 · G M Kenjale Developers
Empire Business Hub
declared completion Mar 2029 · Gajraj Developers
Empire Eternity
declared completion Dec 2021 · Empire Construction
Empire Square Phase III
declared completion Dec 2030 · Empire Properties
Empress Greens
declared completion Mar 2026 · Anand Landmarks

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.